174 RADIOLOGICAL CLEANUP OF ENEWEIAK ALOLL Moonizanon lio Navy task group during the Mobilization Phase arrived on 3 November 1977. The USS JUNEAU and USS ALAMO arrived from Okinawa and offloaded two LCUs, and three LCM-8s.9° During the Mobilization Phase, these Navy opportune sealifts delivered over 29,600 measurement tons of cargo at no cost to the project, a savings tn sealift costs of well over $1,600,000. The delivery of on-atoll critical building supplies, and the use of H&NPTD journeymen to complete some utility systems and other critical facilities significantly improved the status of Lojwa Campconstruction. By mid-October, USASCH was able to report that they were slightly ahead of the original construction schedule. The camp’s 420,000-gallon steel water tank was on hand and was being assembled. In the process, Private First Class Kelvin W. Tea, USA, placed over 15,000 bolts, one of the more formidable tasks in Lojwa Camp construction. Completion of the fresh water and salt water distribution systems was still being delayed by a nationwide shortage of pipe. Consequently, food service, shower, latrine, and sewer facilities would not be completed by the scheduled [8 November 1977 mobilization completion date.96 FIGURE 3-19. ARMY AMPHIBIOUS LIGHTER (LARC). 4 PERMITS: 1975 - 1977 On 13 September 1977, a detachment from Underwater Demolition Team Eleven, commanded by Lieutenant Commander J. F. Sandoz, USN, arrived to begin channel clearance and underwater demolition work 22 September 1977.90.91 In addition to delays in camp construction, extended delays were encountered in obtaining three Corps of Engineers’ permits for the project. There was some doubt that permits were necessary, since the Environmental Impact Statement documented the concurrence of those concerned with the cleanup project actions to be covered by the three LARCs. Despite heavy afternoon rains, they were offloaded in 14 hours. The second shallow-draft barge arrived on 2 October 1977 with October 1975, POD agreed to expedite action to provide permits for: () disposal of noncontaminated debris in the lagoon; (2) clearance (by coral demolition) of channels into certain islands; and (3) crater containment of contaminated soil and debris. POD’s costs in providing permits would be (described in the next chapter). In addition, this team supervised the storage, in an explosives bunker on Medren, of 181 measurement tons of explosives delivered by the Navy ammunition ship, USS HALEAKOS, on On 28 September 1977, a Navy task group consisting of the USS MOUNT VERNON, USS MOBILE, and USS DENVER arrived at Enewetak to deliver 6,617 measurement tons of cargo, including two subsistence, cement, attapulgite, and other supplies.?2 The USS MOLALAarrived on 3 October 1977 and delivered another YC barge. 3 On 12 October 1977, the Navy Water-Beach Cleanup Team arrived at the atoll and set up a base of operations in Building 4 near the other Navy activities The team consisted of one officer and 15 enlisted personnel from Harbor Clearance Units One and Two; and oneofficer and three enlisted personnel from Team 2!, Explosive Ordnance Disposal Mobile Unit One.%4 On 21 October 1977, the USS FORT FISHER delivered 3,161 measurementtons of cargo, including two more Army LARCs. The last proposed permits. Nevertheless, DNA decided to obtain them and, tn financed from cleanup design funds alreadyallocated.?’ It turned out to be more than a simple paper transaction. The U.S. Fish and Wildlife Service, in their action on the permits, requested that DNA meet several conditions, including revegetation of cleared areas; replacement of soil removed in excising plutonium con ’ : i 7 ‘ nesting season; periodic radiation sampling in terrestrial and aquatic resources; and semiannual reports to the Fish and Wildlife Service on radiation found within fish and wildlife.98 Field Command advisedthat the Environmental Impact Statement covered all of the conditions except the

Select target paragraph3