jthe plant was shut down and the decision

—

made to condition it for storage "as is" rather than dismantle the

equipment.
Task Group 7.1 personnel had been phased out in accordance
with the status of their respective projects.

Most of the UCRL

personnel departed following the third and fourth detonations, some
from Task Unit 13 departed after the fifth shot, and most of the
Task Unit 2 and Task Unit 3 personnel left late in April.

Those

remaining personnel from Headquarters, JTF SEVEN, and from Task
Groups 7.1, 7.3, and 7.4 were returned as expeditiously as was possible after 14 May.

PACDIVMATS furnished additional aircraft dur-

ing this period in order to support the increased movement requirements.

The ships and aircraft of Task Group 7.3 and the aircraft

of Task Group 7.4 were returned to their proper stations following
the completion of their respective missions in the forward area to
complete the CASTLE roll-up.

The total cost figure for Operation CASTLE from 1 January 1953

to 31 May 1954 was $96,097,649.

This compares favorably with the

total cost figure of $65,933,163 for a similar period during Operation IVY (9 July 1951 - 31 December 1952) in view of the increase in experimental programs, the number of shots, and the
overall complexity of the Operation-—-CASTLE over IVY.

The fol-

lowing table presents the operating costs, capital costs, and total
costs of the DOD and AEC experimental and support programs for
Operation CASTLE:

153

Select target paragraph3