APPENDIX B
EXHIBIT 7 (Cont'd)
CONSOLIDATED SUMMARY

COMMENTS:

For final accounting the net cost of operation of PG facilities was allo-

cated on a labor basis to the following basic functions of the logistical
contractor:

ana.

NOTE:

Construction
Maintenance of PG facilities

Support and Roll-Up

Support of personnel other than logistical contractor

Scientific Operations includes: Test direction, administration and engineering
for field operation and for field experimental equipment; preparation for
fission andfusion yields
and carrying out of field measurements includingI
, the
~
by radiochemical sampling, reaction histories

neutron miultiphcation rate as a function of time, andtheratere~of Behavior
of detonations using high speed framing cameras; other scientific measure~

ments, cloud motion studies, microbarographic survey, instrumentation,
data reduction and other technical duties involved in test planning and evaluation.

Expendable Construction includes:

Cost of towers, scientific stations, tempo~

rary camps and appurtenances, causeways, marine landing facilities, sub-

marine cable, and other expendable and/or temporary facilities required to
prepare for and accomplish scientific experiments at Pacific Proving Ground.
Direct Support includes:

Work order charges by support contractor for serv-

ices, materials and equipment usage furnished upon specific request of Program and Project Directors.

This report includes only those costs budgeted as Full Scale Weapons Tests,
There was some participation in various scientific programs on a "joint interest basis" by contractor employees of divisions whose activities are not so
budgeted and the cost of such participation is not included in this report, but
has been charged by the scientific contractor to other categories involved.
Common to Scientific Programs item includes: Those costs identifiable with
scientific programs but not identifiable with specific programs, including
such expendable construction as shot towers and other multi-uset scien-

tific structures,
General Expense - Support Task Group includes: Cost of construction of ternmporary camps, docks, roads, etc. related to Support Task Group functions as
distinguished from Scientific Task Group functions.
Programs one thru nine are weapons effects programs sponsored by DOD.
AEC costs limited to reimbursable items except for joint interest participation
in program one.

Net Cost to AEC includes reimbursable work performed for AEC by other

anc

Federal agencies but does not include:

Weapons cost
Any capital expense or depreciation of capital assets
Any share of AEC administrative program costs
Non-reimbursable services and materials furnished by other Federal
agencies