CHAPTER III, SECTIONS 3 and 4
Monthly statistics, showing the estimated
accumulated percentages of physical completion
of Contract items, were compiled and presented

in the form of a bar chart. The Jobsite determined the weight of each construction feature
under a Contract item by dividing each feature’s
direct labor by the total direct labor of the
Contract item as reflected in the original cost

estimate.

Estimated

percentages

of

physical

completion were determined by visual inspection, and the weighted percentage of completion
was determined by multiplying the established

weight by the estimated physical completion.

Further, completion estimates were pre-

pared for each Contract item (of current con-

struction) by the Jobsite Resident Engineer
whenever it was evident that the actual con-

struction costs would vary from the estimated

construction costs. The basis for comparison was

the current cost estimates. If such estimates

were not available, an original (or the latest)

cost estimate was substituted. When this com-

parison revealed that actual field construction
costs would not be within 10% of the estimated

costs, or $10,000, which ever was thelesser, the
Jobsite prepared a completion cost estimate to
reflect the total estimated cost in excess of, or

less than, the current cost estimate. This supplemental estimate was submitted to the Home

Office. If, however, completion estimates were

not reveived in Los Angeles by the tenth of the
month, it was assumed that the latest cost estimate was within the allowable variance.

The over-all percentage or completion, as
determined above, was supplied monthly to the
Holmes & Narver Contract Administrator and
the AEC Field Manager for the accurate evaluation of earned Contract fees.

SECTION 4
INDUSTRIAL RELATIONS
OFF-CONTINENT RECRUITING

was opened in that area, using CSES facilities.

An extensive recruiting program was outlined in April 1953, and early in May the hiring

in this location on the same basis as was used

program for overseas personnel began.

Help-

wanted advertisements were placed immediately

in Los Angeles metropolitan newspapers, and
a recruiting program wasalso inaugurated on 25

Complete processing of applicants was handled
in Los Angeles and San Francisco. Recruiting

started in San Diego on 22 June 1953 and
continued through 30 September, except for the

May in San Francisco and the Bay cities. A
similar program was initiated in the San Diego

period between 1 August and 17 August. Figure
3-3 shows the total number of applicants interviewed and hired from the over-all recruiting
program.

Because office space in the Home Office

“Pp” approval clearances were received
during the week of 7 July 1953 on the first

area during the third week in June.

wasinsufficient to handle the persons responding
to the expanded recruiting, the California State
Employment Service (CSES) granted the use
of their facilities at Eleventh and Flower Streets,

Los Angeles. For the San Francisco area recruiting, the CSES office at 1400 Howard
Street, San Francisco, was used. Complete mechanical processing, i. e., physical examination,
photo identification, and finger-printing of prospective Jobsite employees was established in the

bay area.

Seattle,

Portland,

Salt

Lake

City

and

Denver were also surveyed for possible personnel
but were eliminated from the program due to
the limited number of skilled construction men
available in those areas at the time. Surveys in
the Bakersfield, Ventura and Fresno areas re-

vealed a source of skilled labor, and recruiting

was undertaken in these cities for generating

and distillation plant operators, apprentice engi-

applicants submitted in the initial phase of the
recruiting program at Los Angeles; for the San
Francisco and San Diego recruiting programs,
the first “P’’ approvals were received during

the week of 3 August. (Approximately eight to
nine weeks elapsed between the time an applicant was accepted, processed, and submitted
for clearance before the actual clearance was
received. }

By July 1953 firm commitments were
being made to ‘“P” approved applicants in the
San Francisco area, and overseas Employment
Agreements, allotments and hiring slips were

completed at the Home Office and forwarded
to San Francisco for execution. The Holmes &
Narver personnel representatives at San Fran-

cisco coordinated travel orders with the H&N
representative at Travis Air Force Base and the
Home Office Travel Section. This method of

neers, and electricians. A similar survey in the

handling applicants replaced the previous arrangements by which applicants were brought

power in all crafts, and a recruiting program

the elimination of the customary round-trip

San Diego area disclosed a surplus of man-

Page 3-10

to Los Angeles for processing, and resulted in

Select target paragraph3