CHAPTER II, SECTIONS 6 and 7

Figure 2-223.

Ruby to Sally Causeway

During the storms of November 1953, high
tide wave action caused considerable erosion
of the causeway fill and threatened the pipe
supports. On 9 December 1953 additional construction was approved for protection of this
causeway.

Work

was

started

immediately

and consisted of driving steel rails on fourfoot centers, to an elevation of plus 10.0
feet, with three-inch by 12-inch planking laid

horizontally behind the rails, then back filling
with coral. This bulkheading was completed on

18 January 1954 and proved adequate.

GENE - IRENE CAUSEWAY
Figure 2-224 notes the conditions existing

on the IVY Flora to Irene causeway prior to

the CASTLEtests.

SECTION 7
INTERISLAND CABLES
CONTRACT ITEM A-29
BIKINI ATOLL

erations at the Jobsite, the cable had to be

for future installations to lay cables in shallow

cut at two widely separated points so that it
could be brought to the surface. The two cut
ends were then reconnected by splicing in additional cable to replace the lost section. In
laying cables it was a far simpler operation to
buoy the end of the cable in shallow water at
the completion of the days work, than in deep

105 for OPERATION IVY,it was found fouled
around a coral head in 200 feet of water and it
could not be freed. As this depth of water was
beyond allowable limit for deep sea diving op-

cable was laid in shallow water simplified recovery operations. The laying of cable in shallow
water had the further decided advantage in
eliminating the need for deep sea diving operat-

Experience gained during previous test op-

erations with the installation, testing and re-

pairing of submarine cables laid in deep water
indicated that it would be more advantageous

water (20 to 30 feet). In checking cable No.

Page 2-224

water. When buoys were lost, the fact that the

Select target paragraph3