CHAPTER II, SECTION 5

The permanent construction requirements
are listed under Budget Projects 5026, 6001
and 6011, and the items undertaken are indicated in Figures 2-5, 2-7, and 2-9. They are also
shown graphically in the camp site plans of
Elmer, Fred and David, Figures 2-199, 2-200,
and 2-201. The cutoff date for reporting permanent construction is dependent upon the
date the project is completed and: does not

necessarily coincide with the completion of a

test operation.

To engineer the structures added to the

permanent base, maximum use was made of

prefabricated buildings. The all-aluminum building (Pacific Iron and Steel type) has practically
become standard for such base structures as
barracks, mess halls, offices, and other camp

buildings. These buildings have double roofs
for weather protection, and their most notable
advantage is that they virtually do not require
maintenance. The steel frame building with aluminum siding and roofing (Butler type) has
become standard for warehousing and shops;
this type of building lends itself well for these
services. Exceptions to the standard designs were
those for special-use buildings such as the chapels and the guest house on Fred, which were
wooden-frame structures, and for the explosive
storage facilities on Rex, which were
standard igloo-type steel magazines.

Navy

Due to the relatively low elevation of the
islands and flat gradient of the normal ground
surface, the drainage problem in certain areas
was given special attention to ensure that warehousing facilities would be accessible and useable during all weather conditions. With respect
to the construction of all buildings, there were
no unusual problems except for those arising
from a compressed construction schedule for
those items included in Budget Project 6011.
It was recognized early in the program that to
have the facilities most urgently required for
REDWING completed on time, it would be

Figure 2-195.

Guest House - Fred

ment of steel and aluminum components of
buildings and by careful surveillance of trans-

portation conditions to ensure adequate cargo

space, the flow of materials started in September and was completed in December. As building materials began to arrive, men and equipment were concentrated on these projects and
the work was well under way by December
1955. At this time, as previously noted, it was
necessary to defer construction of certain nonvital projects in order to complete vital scientific test facilities on scheduled dates.
A critical situation developed with respect
to adequate storage and distribution of jet fuel
because of delays in expanding the Fred POL
system. A major contributing factor to the
difficulties experienced with this project was
the delays in the development of criteria by
the U.S. Air Force. Several major revisions to
criteria were received during the preparation
of design in the Home Office. Also, a number
of field conditions were not adequately provided
for and a number of field revisions to the

necessary to initiate procurement of construct-

ion materials as early as possible after the start

of the Fiscal Year, 1 July 1955, when funds

could be made available. Therefore, in May
1955,

the

Deputy

Director,

Test

Division,

authorized advanced planning and design so
that necessary approvals from Using agencies
could be obtained and purchase orders awarded
without delay. Though unavoidable under the
established funding and design approval process,
the funds could not be made available until
11 August 1955, and final approval of drawings
could not be given until late September and
early October 1955. However, authority was
received to proceed with preliminary work in
advance of final approval of drawings. This
preliminary work consisted of demolishing ex-

isting buildings, site grading, and pouring concrete foundations. By expediting the procure-

Figure 2-196.

Jet Fuel Stand - Fred
Page 2-207