CHAPTER II, SECTION 5

SECTION 5
PERMANENT CONSTRUCTION
A long range plan* for improvements of the

PPG facilities and utilities was initially prepared in October 1952, then revised in 1954

after CASTLE,and again in June 1956 as REDWING neared completion. The conclusions and
recommendations contained in these reports
were predicated on sound and reliable information resulting from the experience with all
phases of engineering, construction, operation
and maintenance. Each plan covered those items
considered necessary and desirable for each succeeding test operation. This Completion Report
covers the items undertaken from 1 July 1954
through 30 July 1956. When the Long Range

Plan of 1954 was formulated, all eventualities
of the next operation could not possibly have

been foreseen. Therefore, in addition to items
recommended in this plan, a number of items
had to be undertaken due to increases in operational requirements and participating personnel

During REDWING, the parking area was

increased by the addition of a southeast apron

to provide for an increase in plane operations.
The total apron area of approximately 300,000
square yards was paved with a 60-40 emulsion
of bitumuls mixed with graded aggregate. The
asphaltic concrete was deposited in windrows
and spread with a blade. This operation was
followed by rolling with steel rollers and finally
with wobbly-wheel and compaction rollers. A
40-ton compaction roller was constructed in the

field, largely from surveyed parts of other
equipment. This roller consisted principally of
eight large rubber-tired wheels and a frame on
which a steel box, loaded with limonite concrete

to provide the 40-ton load, was carried. The

results obtained were good. One sub-base failure
occurred which was found to be due to a rotting
coconut log deeply embedded. This area was

firm at the time of the CBR tests. There were

for Operation REDWING beyond that anticipated when the plan wasfirst prepared.

no failures of the parking apron base course or

Shortly after the completion of Operation
CASTLE, extensive improvements of the Fred

After the completion of Operation CASTLE, the Fred runway showedsigns of cracking
at the surface. The runway was periodically
shut down, the surface thoroughly cleaned, and
a sand-seal coat of approximately one-quarter
of a gallon of asphalt per square yard was applied. This operation was followed by rolling
and later by sweeping to remove the excess
sand. The new parking aprons were similarly

airfield were undertaken. This eventually involved the asphalt paving of approximately

300,000 square yards of the airfield parking
aprons and seal coating approximately 114,000
square yards of runway.
. The parking aprons were, for the most

part, composed only of a thick dust pallative
which, under repeated use during CASTLE,
had become broken and unsuitable for airplane
operations. Using a survey grid system, the

paving during Operation REDWING.

treated for protection of the surface from jet

plane blasts. This seal coating was effective in
that patching was necessary only during the
latter half of Operation REDWING.

entire existing apron area was tested by the

CBR method. These tests indicated that the

aprons were substandard and would be parti-

cularly unsuitable for jet plane operations. The
dust pallative of approximately two inches thick

was removed and the base course thus exposed
was tested again. The base course was removed

in all areas that were found unstable, and after
recompacting the sub-base, a new base course
of graded aggregate was placed. The base course

was compacted with a minimum CBR requirement of 80 per cent, but in 90 per cent of the
tests the CBR’s rose to 98 per cent. This assured
adequate support for wheel loads up to 100,000
pounds. In areas where the CBR’s indicated
satisfactory stability, the surface was watered

and rolled to grade preparatory to the application of asphaltic concrete.

* Proposed Long Range Improvement Pro-

grams dated October 1952, June 1954, and

June 1956.

Page 2-204

Figure 2-188.

Jobsite Fabricated Roller

Select target paragraph3