CHAPTER Ii, SECTION 4
In order to prevent surface disturbance by
truck tires while spreading the base course,
sandy organic top soil, which acted as a sealer,
was placed over the sub-base to an average
depth of 0.2 feet. This material, which was also
used under the 4-inch surface course of the
airstrip shoulders, compacted well and had a
CBR value of 30 per cent at optimum moisture.
The average gradation of material was as folows:
Sieve Size

% Passing

36
+ 4
+ 8
+ 16

100
80
77
69

# 50

16

#. 30

38

#+ 100
# 200

10
7

Rock for the base and surface courses was
obtained from the southern tip of the island.
Crushing operations were started on 30 December 1954. The material was produced in a plant
consisting of a primary and secondary crusher,
in order to obtain the required 4-inch maximum size aggregate. Base and surface course
aggregates were hard, durable mixtures of coral
rock and sand, with a high bearing capacity
either wet or dry. Placement of the 4-inch base
course started on 1 February 1955; compaction
was obtained by using sheep’s foot, grid, wobblywheel rollers and a Jobsite-built 45-ton pneumatic roller. The runway strip was completed
on 13 March 1955. Average gradations of the
base and surface course aggregate were as
ollows:
A. Base course aggregate Sieve Size

% Passing

4 Inch
2 Inch
1 Inch
% Inch
# 4
# 10
+ 40

100
64
49
39
29
25
17

# 200

0-5

# 80

The parking apron, helicopter mat, and the
end of the runway from Station 0 to Station 3
received a top coat of approximately 0.2 gallons
of bitumuls per square yard. A seal coat, consisting of 0.6 gallons per square yard mixed into
beach sand, was then applied to a thickness of
% inch. This seal coat was rolled and sanded
as necessary. A total of 38,346 gallons of bitumuls was used.
On 15 March 1955, an airplane landed on

the airstrip for the first time. By 10 April 1955
the buildings were occupied, and on 28 May
1955 all work was completed. The job as completed required 500,000 square yards of site
clearing and 53,414 cubic yards of borrow materials. The air operations building, of wood
frame construction finished with plywood siding
and aluminum roof, was 30’ x 60’ with a 9-2” x
12’-6” lean-to for a latrine, and with a 10’-6” x
10°-6” control tower. The fire-crash station of
similar construction was 24’ x 36’, with a vertical
clearance of 15 feet. The hangar building, 50’ x
75’ with vertical: clearance of 20 feet, was fini-

shed with corrugated aluminum siding and roofing.
The California Bearing Ratio Method was
used on the airstrip to determine shear strength
and bearing capacity. The test locations were
uniformly spread throughout the area. A total
of 36 tests was made for the base course with
Maximum readings of 100 obtained at three locations and with a minimum reading of 38 and
the average of all tests being 69. A total of 49
tests was made for the surface course with maximum readings of 100 being obtained at many
of the test locations, with a minimum reading
of 75 and with the average of all tests being
93. The results of these tests indicated that
uniformly high bearing values were obtained.

4

B. Surface course aggregate Sieve Size % Passing
1-% Inch
1 Inch
% Inch
+ 4
+ 10
# 40
+ 80
# 200
Page 2-158

100
93
63
4}
33
11
4
1

Loose dry unit weight
90.5 ibs./cu. ft.
Rodded dry unit weight
101.5 Ibs./cu. ft.

Rial edt PR

eo

~& ot ie

Figure 2-138. Operations BuildingNan Airport

Select target paragraph3