40
Approval was received on 26 August 1954,
for the preparation of working drawings and
original estimates for the temporary camp facilities contemplated for construction at Nan.
In September 1954, approval was also received
for the plant and equipmentprojects for Fiscal
Year 1955, amounting to approximately $1,500,000.00, the major items of which included the
deep water pier at Elmer, and the eleven bar-

racks at Fred. The release of this work permitted
a fairly constant level of employment during
this transitional period.
Planning for the construction on Nan contemplated advance stockpiling of material and

equipment at the site, prefabrication of building assemblies at Elmer, the reactivation of

equipment in Station 70 for the early establishment of interatoll communications, the reduction of the existing radioactive hazards at the
campsite, rehabilitation of the Peter-Oboe air-

strip for limited service, the establishment of
a beachhead camp from which the construction

program could expand, and priority construction of an airstrip suitable for landing C-47
type planes. To provide the logistic support,
arrangements were made through AEC channels
for utilizing an LSD type ship for the initial
landings and the continued use of an LST
thereafter. The LSD was selected for the initial

landings inasmuch as heavy equipment, such
as cranes, could be transported without being

dismantled, and because the tranfer of LCU
and LCM craft could be more easily effected.
Dismantling of cranes is necessary when an LST
or conventional type vessel are used. The con-

tinued use of the LST was essential for the
establishment of an Eniwetok-Bikini shuttle service, since construction at Bikini was predicated
on the fact that the main supply and repair

base would remain on Elmer.

On 24 September 1954, construction of Increment No. 1 of the Nan camp (250-man

capacity) was authorized with instructions
that the housing tents and latrines were to be
erected only on an as-needed basis to meet
population requirements. The first task group,

consisting of 29 H&N employees and two AEC

representatives, departed Elmer on 9 October

1954 in the USS Belle Grove (LSD). This task
group was supported at Nan by an LCU outfitted as a houseboat during the period when the
LSD madethree roundtrips for the movementof
material and equipment. The LSD wasrelieved
by LST-618, which arrived at Jobsite on 30
October. During the month of November, the

operations preliminary to the establishment of
a beachhead camp continuedas previously planned. The beachhead camp was ready for oc-

cupancy by 5 December and 34 H&N men were
janded there on that date. This force was gradually augmented, and by 1 January 1955, there
were 150 men employed in Bikini Atoll.

CHAPTER!, SECTION 1
With the authorization for construction of
the Nan camp, various studies and appraisals
were undertaken to determine the engineering,
construction and logistic problems that would
be involved in an Operation with a scientific
structures program similar to that of CASTLE;
these studies were made with the expectations
that firm requirements for causeway construction would be available by 1 April 1955, and
for scientific stations, by 1 July 1955. Included
in these studies were the best means for reducing radioactive levels at probable construc-

tion sites; the feasibility of using bases afloat
in lieu of shot-island camps; the condition of
existing scientific stations, submarine cables,
and causeways; and the availability of shot
barges and high speed personnel boats.
Because of the widespread destruction and
contamination of the land base camps caused
by CASTLE detonations, the subsequent difficulties in operating from shipboard, theinitial
high cost of temporary shot-island camps, and
the uncertainty of finding habitable land areas
in the vicinity of shot-islands, consideration was

given to the practicability of using quarter boats
instead of shot-island camps for both the construction and operation phases of REDWING.
it was proposed that should such type craft
be acquired, they would be anchored fairly close
inshore at the major construction sites and

would be moved to sea during evacuation. These
vessels were to be completely staffed by the
Contractor. Investigation and inspection of the
U.S. Navy-type barrack vessels indicated that
these craft were possibly suitable. Funds were
made available in the Fiscal Year 1955 Budget
for activation of one of the vessels. Subsequent
developments, particularly the ease with which
radioactive levels at camp sites were reduced,
led to the abandonment of this project.

Through the months of December 1954 and
January and February 1955, work progressed
satisfactorily on approved items of construction
in both Atolls. By the middle of March 1955,
construction at Nan was ahead of schedule; the
airstrip was 78% completed, and C-47 type

planes were landing on regularly scheduled
flights. The interatoll teletype and radiophone
communication systems had been activated and
the work in connection with housing, messing,
shop, warehouse and POL facilities was well

under way. At Eniwetok Atoll the airfield improvements program had been completed, progress on the Elmer deep-water pier and the

barracks on Fred was ahead of schedule, the
Elmer and Tilda airstrips had been rehabilitated,
and a considerable number of miscellaneous

items of construction had been undertaken. On
15 March 1955, there were 850 contract employees at the Proving Ground.

Page 1-3

Select target paragraph3