pleted the footings for the 200-foot tawor while quartered aboard ship,
moved ashore with the company and began tower erection.
Surveying was begun on 20 January when Lt. Cmdr. Pfau and hia
survey party staked out the Hartmsnn line, which also served as a part
of the base line for the triangulation schame. Due to high wimds and
bad weather, there was a delay of about one week when no msasurawnts
could be made. This was overcome by using a canvas wind shield 3 ft.
high and 180 ft. long, stretched along the windward side of the measuring
tape and manned by 18 enlisted man. By using this system, the initial
concrete building was located and layout completed on 29 January. All
other layout was finished 2 February.
Constructionwas initiated January 21 when excavation for the winch
base was completed anc concrete forms were set in place. Concrete for
this structure WSS poured the following Saturday, 24 January. One Week
later, 31 January, base slab forme were set h place for the timing
station. Since the base slabs for all structureswere to be of

concrete,

ueing local beach run coral aggregate, It was decided that all base slabs
would be finished before ●ny wall end roof forms were placed. Accordin@y,
the base slabs for all structures were completed Saturday, 7 February.
Meanwhile, wall and roof forma ●nd reinforcing steel were being set in
place at the timing station. All form were completed by Friday, 13
February, and

●

monolithic pour of 83 cubic yards of concrete waa made

using local beach run coml aggregate graded ●t approxinmtely 6s% passing
a ~ inch sieve and 35% passing from 24 to ~ inch sieve. The mix was
1:2:5 by volume. The above specificationswere follcmed as closely as

Section XVI
. —..
---

Select target paragraph3