GUAM
F&SNO.

TITLE

29001

HF Communications Simulation Experiment - Subtask A611

USER

STRUCTURE/FACILITY NO.

TC

None

FUNDING
AGENCY

DASA/

RDT&E

SCIENTIFIC STATION NO.

($000)

[13-3-1

ENGR

PROC

CONST

GO+105

TOTAL

FURN

Engineering costs included in F&S Number 21003.

Estimate 12/65

TOTAL

8.3

8.3

8.3

8.3

PRIOR YEARS
ENGINEERING
Drawing:

Completed.
113-002-C]

POST -GO
PROCUREMENT

To be accomplished.

CONSTRUCTION

Test Command will furnish two 110-ft. high Log Periodic

Ionospheric antennas, and one instrument trailer.

The contractor will furnish

one 20 kw, 120/240 volt, 60 cycle, single phase, low speed (1250 rpm) diesel

generator for use as a back up power source. Primary power will be provided
from existing military or local sources. Construction will probably be accomplished by a local contractor.
The contractor will perform the following: a) prepare a cleared, flat, 405 x 590ft. unobstructed area for the TC erected 110-ft. high Log Periodic lonospheric
antennas which will have a ground screen that extends into the sea;

b) construct

concrete antenna bases, as designed by TC in the field; c) provide longeron pads
and anchors for the antennas; d) site the instrument trailer; and, e) install the
generator and complete the electrical hookup to instrument trailer. Refer to
Figure A-26, Appendix A, for site location. Four scientific personnel will be

assigned to Subtask A611 at this site.

29-3

_

FOD GO+125

PRE-GO

EAO 11064 POST-GO

4101-61

Bop

VOL II
April 1909