Ne CHAPTER Hl, SECTION 5 Figure 2-107. Station 1203 - Progress Photograph CONSTRUCTION. Work was scheduled to commence on 15 June and to be completed by 31 January. Actual work started on 15 June and was completed on 30 November. Figure 2-107 shows status of work on 10 September. Figure 2-108 shows pipe array with horizontal and vertical hardware in place and 1eady for alignment. Correction to pipeline alignment for curvature of the carth’s surface was at first incorrectly applied in the vertical alignment of this Station. The error was detected by tele- scope and gamma ray source checking, and corrected. Stations 2220 and 2230 were satisfactorily aligned by precise survey methods introduced as a result of the experience with Station 1203. Some trouble was experienced with the wood frames and hardware. With the number of pipes to be supported, the frames were slightly under-designed. The hardware likewise should have been sturdier. With alternating 4 t - { %+ ¢ meewan metBn Lage: Seeels al Figure 2-108. Station 1203 - Hardware Installed ;r ur doe ettraiPieters Bone oP A EO

Select target paragraph3