SERIES SCHEDULE
-2-+
4 days survey Utirik
2 days survey Taka ({ncludes packing and travel)
_i day travel to Kwajalein
err
24 DAYS
Crew change at Kwajalein.
3RD SERIES
1 day travel to Ailuk
6 days survey Ailuk
1/2 day pack and depart for Mejit
1 day survey Mejit
Ll day pack and depart for Jemo
1 day survey Jemo
{J3 day pack and depart for Likiep
7 days survey Likiep
2 days pack and depart for Ujelang (2 days travel)
S days survey Ujelang
“1 day pack and depart for Enewetak (16 hrs. travel)
__. SURVEY COMPLETE
26 DAYS
27 IST SERIES
24 2ND SERIES
26 3RD SERIES
77 TOTAL TIME REQUIRED FOR TECHNICAL SURVEY