DOE.
This phase will be limited to 300 EC-121 flight hours
including transits to and from the survey site.
c.
Phase II of the survey will be accomplished by deploy-
ing the designated base support ship, USNS WHEELING
(TAGM-8),
with embarked SH-3G helicopter detachment, technical and support
personnel to the Northern Marshall Islands.
The current plan is
to limit USNS WHEELING (TAGM-8) to 77 days on station and 57
days in transit including transits to port for logistics
replenishment and reprovisioning or some reasonable combination
thereof.
While on station, a twelve-hour working day is agreed
to, recognizing the resulting additional overtime costs.
The
Radiological Survey as planned will be further limited to 556
total flight hours for the assigned SH-3G helicopters including
those flight hours provided for predeployment training, transporting personnel and equipment ashore and for other administrative purposes as required.
Upward adjustments to the fore-
going limitations amounting to over 10% will require formal
amendment of the MOA.
ad.
.
Appendix I is an overview of the three
(3)
series
(A,
B and C) of radiological missions that will constitute Phase II
of the survey.
complete survey
6.
At Appendix II is a framework schedule for the
(Phases I and II).
SURVEY TASK GROUP ORGANIZATION.
DON, DOE and DOI resources
dedicated to the accomplishment of the Radiological Survey will
be organized into a Survey Task Group as follows: