6.14

SCHEDULE
The longest lead time item is considered to be the AN/TPQ-18 Radar.

The site preparation and utilities portion will be completed prior to
the arrival of the instrumentation,

The other systems will be installed

and checked-out during the installation and checkout time period of the
radar.

The integration for all of the systems will occur during the

time period noted for the radar.

AN/TPQ-18 Radar Schedule

Sept 66

1 Aug 65

|

Fabricate

|

|

Ship

Nov 66

|

| Install &
Checkout

Mar 67

|

May 67

|

| Sys.
Integration

Ops

Contract Let

Readiness Date

Due to the schedule, FY 66 funds must be provided for the
procurement of the systems.

-21-