TRUST TERRITORY
PRELIMINARY AND ROUGH ESTIMATES
REGARDING RETURN TO BIKINI

February 1968

Suggested Phasing, Time Table, and Costs:

A.

Giving the "go-ahead"; consult with people. Take representatives
to Bikini. Develop plans. Get outside help regarding village
planning.
Time:
Cost:

B.

criteria.

"Contract", Leb Island village construction

Wood frame school.

1 year
$410,000.00

Move from Kili. Physical exams in Majuro.
Relocation allowance.
U.S.D.A. surplus feeding program for 1 year.
Time:

Cost:

E.

5 years
$165,000.00

Construction program.
Time:
Cost:

D.

90 days
$5,000.00

Advance party, bushing, planting, and later grove maintenance
program. Eneu as base.
Relieve advance party after six months.
Replanting time:
1 year. Grove maintenance for 4 years. Construction of interim camp site.
Time:
Cost:

C.

,

14 months

$45,000.00

Total time span until resettled and off government subsidy:
Total cost of resettlement program:
$625,000.

7 years.*

Some thought should be given to an economic loan program for the Bikinians
to help them achieve self-sufficiency.
The cost of such a program is not
included here. Their proven ability as producers (e.g., the famous
Kili handbags) of much desired handicraft should establish them as "good

loan risks."

,

* 1 year planting.
6 more years for palms to grow until bearing nuts.
People move to Bikini ar sixth year after replanting. Will be on
government subsidy for one year.

~