Establish the capability at Taongi to accumulate weather information
and data. This station should start as soon as possible and continue
until just prior to the Hardtack Operational phase. This viewpoint
has already been expressed in a letter dated 21 January 1957, Dr.
G. W. Johnson to Captain K. Musick.
Immediately determine if an airstrip is justified since this would

constitute the major effort ashore and fixes the scale of effort required from the contractor at Teongi.

Fix the method and responsibility for the opening of the channel as
soon as possible after the completion of the preliminary inspection
and oceanographic survey trip.
5.

Accomplish the task of choosing and obtaining the diagnostics ship

just as early as possible in order to begin the timé consuming
experimental outfitting and reconfiguration soon.