6.

SURVEY TASK GROUP ORGANIZATION.

DON, DOE and DOI

resources dedicated to the accomplishment of the Radiological
Survey.will be organized into a.Survey Task Group as follows:
a.

Project Manager.

COMPMTC was designated Project

Manager for logistics support to the subject survey in CNO msg

0100072 APR 78 and will continue in this capacity through
project completion, coordinating and providing, on behalf of
. DON, all logistics support required by DOE for the accon-

plishment of survey objectives...

b.
Aerial Photographic Task Element.
The Officer in
Charge of the EC-121 aircraft detachment will report for operational control directly to the Project Manager for the
conduct of Phase I of the survey, and will function as the

-

primary point of contact for the DOE designee having technical
direction responsibilities for the conduct of Phase I of the

survey.
Cc.

Aerial Radiological Task Element.

This Task Element

will accomplish Phase II of the survey utilizing USNS WHEELING
(TAGM-8), assigned helicopters and associated support personnel and equipment.

(1)

Logistics Support Task Commander.

Embarked in

USNS WHEELING (TAGM-8) will be a-Logistics Support Task
Commander (LSTC) who will function as the primary point of
contact for the DOE representative exercising technical

direction responsibility for the conduct of Phase II of the

survey.
The LSTC will have overall operational control and
Management responsibility for DON provided logistics support.
DOE representatives will channel requests for survey logistics
support through the LSTC who will then coordinate the efforts
of the USNS WHEELING (TAGM-8) and the OINC of the helicopter

detachment.

The LSTC is further designated as the Sponsor

Designated Representative

(SDR) as defined in reference

(a).

(2)
PMTC Technical Representative.
The Project
Manager will designate an embarked PMTC Technical Represen-.

tative who will act as primary advisor to the LSTC on logis-

tics support matters.
The PMTC Technical Representative will
assume the functions and responsibilities of the LSTC/SDR in
his absence.
(3)

Master,

USNS WHEELING

(TAGM-8).

‘The ship's

Master will have absolute authority and responsibility for the

safety of his ship and embarked personnel as prescribed in

teference

(a) .while responding to the operational requests and

xecommendations of the embarked LSTC/SDR.