CHAPTER It, SECTIONS 1-1A
field inspectors to the greatest extent possible.

The weekly progress report detailed activity
on open construction work orders which reached

4 maximum number of 337 on the Eniwetok
Atoll and 339 on the Bikini Atoll for a total

of 676.

SECTION IA
SURVEYS
Surveys by Holmes & Narver at the Pacific

Proving Giound were initiated at Eniwetok

Atoll in February 1949 with the topographic
mapping of project islands for design ‘surposes.
As additioral personnel arrived, the activities

of the department expanded to include a hor-

izontal control network, additional torpograpny,
hydrograph, construction lafout, and special
surveys to satisfy scientific requirements and to
provide assistance to Users. Surveys at Eniwetok were a continuation and expansion of

these activ:ties to fit the special needs of three
test operations.

With the expansion of the PPG to include
Bikini Atoll, a survey progrem was initiated in
this area following the same general pattern of
surveys previously performed in the Eniwetok

Atoll area. The majority of the survey personnel
were stationed at Bikini Atoll duting the
CASTLIE program with a maximumof six field
parties and supporting office personnel. The
smaller program at Eniwetok Atoll was served
by two field parties with some transfer of personnel between areas to meet peak work loads.

The sequence of surveys at both areas was

dependant’ on priorities for the services of the.

department. As construction layout proceeded
simultanecusly with design and contra) surveys,

it was not possible to follow the normal pro-

cedure cf first establishing horizontal and
vertical control and then proce -ding in sequence
through design surveys and ccnstruction layout.
This condition did not permit maximum efficiency in performing the design and control surveys,
but as construction layout was kept on a current

basis at all times, the procedures used were just-

ified. The earlier surveys were covered in detzil

in reports of OPERATIONS GREENHOUSE
and IVY, and the following is primarily a description of survey activities at Bikini Atoll thr-

ough the CASTLE program. In view of the recoverabilitvy of the work and its probable future
value in any use of the area, however, sufficient
historical summaryis given to evaluate its cartogrephic significance.

HORIZONTAL CONTROL — ENIWETOK
ATOLL
A horizontal control scheme was es:ablished in 1949-50 covering the eastern portion of the

Atoll. This scheme was expanded in 1951 and
1952 to include the entire Atoll and consisted
of primary network of second order triangul-

ation stations supplemented with third order

stations at locations of lesser importance. Test

operations destroyed some of the original
stations and new stations were established, as
required, by expansion from the remaining por-

tions of the network. Records of these surveys

are included in the completion reports for OP-

ERATIONS GREENHOUSEand IVY.

PREVIOUS SURVEYS. A study of previous

survevs within the Atoll was made and some

features of these surveys were utilized in establishing the scheme. The available records of these
surveys are included in “The Report of the Engi-

neer, Joint Task Force SEVEN, Part 2,” dated
1948.
The earliest survey was completed in 1944
by the USS Bowditch to control the hydrographic mapping of the Atoll. This survey was
of third order accuracy. and as mostof thestations were not on project islands it was not ad-

aptable to requirements of this project. However, the Bowditch geographic position of Stat-

ion North Base on Runit Island and the azi-

muth of the line Station North Base-Stacien

Sand becamethe origin of positior. and azimuth
tor the later surveys.

A survey was completed in 1947-48 by

Joint Task Force SEWEN, consisting of a limited scheme covering the eastern portion of the
Atoll. The scheme was reported to be of first
order accuracy but it was only because of its
limited extent that it could be considered to Le
of such high order. As the south ena of the original (USS Bowditch) base line had been destroyed, a new base line, North Base-Runit, was

established and the azimuth of this line was

computed from its relation to the line North
Base-Sand. Expansion of this scheme involved
re-occupation of all of its existing stations and
it became obvious that to meet project
uirements, a substantially new and stronger scheme

was necessary which could be expanded as rquired.

1949-50 HORIZONTAL CONTROL SURVEY.

This scheme was designed to meet the control

requirements of. OPERATION GREENHOUSEand to be adaptable to future expan-

Page 2-6

ad

Select target paragraph3