CHAPTER Ii, SECTION 1.
G) were received from LASL and consisted of:
(1) two towers, one 275 feet high on Elmer and
the second 300 feet high on Nan; (2) a dehumidified timing and communications building at
Nan; (3) and a small camp and helicopter mat
at Nan. A r-quirement for the design of a hydrogen dual liquefaction plant complete with utilities and services was also received in January.
Increases in operational population at both
Fred and Elmer were now apparent. Additional
water and power requirements for these permanent base camps were investigated and studied.
In March 1943, the recommended additional
high-capacity, portable distillation units were
authorized as temporary support facilities. A
1000 KWdiesel generator at the CMR powerhouse on Elmer and a submarine power cable
connecting Elmer and Fred were also recommended and authorized to absorb peak loads at
Fred.
On 15 April 1953, the Field Manager, AEC,
announced to the Users the necessity of having
design criteria in final form by 1 May 1953. As
a result, large quantities of data were received,
but there were many subsequent major changes
which modified a large percentage of this data,
and in some cases there was a lack of sufficient
information upon which to hase completed designs at that time. The manner in whichthis is
broadly inhibiting to the Contractor is illustrated by Scientific Station 20 - site Charlie, in
which, pending only a column rearrangement,
floor plans could not be laid out, structural steel
could not be designed or ordered, and even field
work could not be started until foundation and
piling requirements were known.
As the original scope of UCRL facilities
was revised, so also was the original scope of the
EGEG program modified. The Hydtogen Dual
Liquefaction Plant was deleted; the 275-foot
tower on Elmer was deleted and four 75-foot
towers were added; the Nan timing and communications building (Station 70) was greatly
increased in size and a bunker type power plant
added.
Incomplete data and revisions out of schedule have an impact on costs since they tend to
compress the accomplishment time into such
factors as overtime and unbalanced inventory.
Experience has shown, however, that the momentum of scientific progress, the impulse to
seek test perfection, and the necessary periodic
re-evaluation of the test facilities in terms of
constant refinement of data, appear to make
such changes and revisions inherent in the approach to an Operation. The necessary adaption
was made and by the end of Sentember, the
structural, mechanical and electrical design
work was practically completed.
Minor changes of criteria were submitted
and revisions to details of approved drawings
Page 2-2

were requested through October aad into Nov-

ember.

New designs were requested efter 15

November, notably the transmitter building and
antenna array on site Nan (Station 7400). Due
to the time element, these Stations could only
be constructed by designing around surplus and
maintenancestores at the site. This was done.
The Home Office Engineering manpower
required for the Scientific Structures Program
is shown by the Engineering and Drafting Manpower and Progress Chart, Figure 2-1. It will be
noted that the major work load for the four
months of May, June, July and August, was
more or less constant, with the peak load of
10,000 man hours per month being reached in
July. The civil engineering peak load occurred
in October when the final calculations were
made to convert the Scientific Station co-ordinates, bearings, and distances to the precise
Bikini Atoll survey grid.
FOUNDATION and SOIL INVESTIGATIONS.
In order to design foundations properly fer certain massive Scientific Structures, and to control the critical limits of settlement required, a
series of test borings were made on critical islands: 13 borings on 19 islands of Bikini Atoll
and two borings on islands of Eniwetok Atoll.
The drilling was accomplished by using
rotary-wash type drilling equipment. Ten of the
borings at Bikini Atoll extended to a depth
of approximately 100 feet below the ground
surface. The other three borings varied from 66
to 87 feet. The test drilling was started in March
1953 aud completed in May 1953.
The borings indicated that only slight differences existed in the structure and sub-surface
characteristics of various islands. Observation as
well as test results from the field laboratory

showed that none of the borings developed soil

mechanics unsuitable from a foundation standpoint. These borings encountered no voids but
did not rule out local void characteristics sometimes present.

Undisturbed core samples of the soils pene-

trated were extracted; alsn, representative loose
samples were obtained during the course of the
drilling for chemical analysis. All soils encountered were classified by visual and textural examination in the field; these classifications were
supplemented by sieve tests and inspection of
the samples in the test laboratory. These undisturbed core samples were subjected te a series
of tests to determine the strengths, compressibilities, and phvsical characteristics of the soils.
Direct shear, friction and consolidation tests
were performed. In conjunction with these tests,
the moisture contents and densities of the samples were determined. To aid in identification
and classification of the soils, mechanical anal-

ysis was performed on the loose samples.