CHAPTER H, SECTIONS 18-2
for particular

Inspection that all work was completed
and met requirements.

6. Concrete placement approval, informing
Construction that Inspection had checked all items and approved the work as
ready for placement of concrete. This
permitted reasonable control to avoid
any unauthorized or unscheduled pours
which are prone to oveur where widely
scattered operations are involved.

9. Inspectors’ check-off list, similar to the
check-off list as used by the U.S. Army
Engineers for inspection. This check-off
list represented the minimum requirements of the inspection standards.

ingredients to be used

purposes.

-1

. Inspection punch fist, used by inspectors
to note items of work yet to he accomplished or corrections required.

8. Completion report, the final notice bv

10. In addition, a daily log or diary was
maintained by each inspector and by
the Material Testing Laboratory.
Mechanival and clectrical features for
Scientific Stations were tested for operation
to the satisfaction of the User.

SECTION 2
CONSfRUCTION
Preliminary consideration of construction
for OPERATION CASTLE was inaugurated
in June 1952 when a request was received from
the Field Manager for a reconnaissance and
report for facilities on Bikini Atoll. This request
resulted in a carcful study of construction equipment and other long delivery items for the purpose of evaluating the capatnlity of carrying
on construction work at two widely separated
sites, Eniwetok and Bikini. Since reinforced
concrete construction was to be one of the major
items, the requirements for large scale aggregate
production equipment were finalized and orders
placed for the delivery of two crushing and
screening plants.
In September 1952 a directive was received
to proceed with the establishment of a heachhead camp on site Tare at Bikini and the construction of a 250-man temporary camp capable of being expanded to a 1000-man camp,
a 4500-foot by 150-foot airstrip with connecting
causeways, and beaching facilities for LSTs and
smaller marine craft. Since this requirement occurred as the construction phase o1 IVY was
drawing to a close, it was possible to staff the
initial Bikini effort with manpower and equipment as it became surplus to the needs of the
work at Elmer, on Eniwetok Atoil.

erage radiation level in this area was 50 to 95
mr per hour in December, necessitating close
Rad-Safe control over men working in this
area, Some experimental work was done toward
decontaminating the areas and it was found
that the most satisfactory results were obtained by removal of vegetation and up to 12 inches
of the top soil in areas affected.
Attempts
to decontaminate concrete slabs in the camp
by flushing with salt water were not too satisfactory in that most of the readily removable or
soluble irradiated particles had been already
washed off by normal rains. The early stages of
construction were carric! on by forces based
at Elmer and flown into Ursula each morning
by plane. Later the forces were based on an
LCUequipped as a house boat. By May 1953
the radiation level had been lowered by decontamination and decay to a point that allowed
the forces to live ashore in a camp indefinitely,
within allowable dosage.

In November 1952 a directive was received
from ihe Ficld Manager to establish a temporary 200-man camp at Ursula and to proceed

These two requircments for camps provided the pattern for planning bases cf operation
for CASTLE. The entire scope of the Scientific
Program was not known at this time; however,
cnough information was available in January
1953 for preliminary planning of requirements
for manpower, construction materials, air and
surface transportation, communications, shipping, and construction equipment. Advance
material estimates were prepared and orders
placed for common usage construction materials and additional cquipment.

usable land. Figure 2-26 shows the radioactive
crater partially filled on Ruby. This picture
was taken on 25 March 1953 and work was
underway to lower the radiation level. This
work was complicated by the fact that the av-

In April 1953 the scope of Scientific Structure construction for CASTLE was well delineated for both atolls, and final scheduling of the
work, location of the concrete batching plants,
establishment of material stockpiles, allocation

with the filling of the Ruby Crater to create

Page 2-51

ee eeeis

——!
ee

ame ae eed ia tins,

=m.

Select target paragraph3