RUNIT MEETING
AGENDA

or

1.

INTRODUCTION - COL Treat
ACKGROUND/REQUIREMENT/PLAN - COL Treat

2.

a.

View
Graph

BACKGROUND

Enewetak Evacuated - 1947
Tests 1947 thru 1958
Runit worst - 18 tests
Return to TTPI - 1972

Auth for Cleanup - 1976
Limitations - 20 or +

b.

REQUIREMENT

View
Graph

1.

Hazardous nonradioactive debris

5.
6,

40-400 pCi/g - case by case
<40 pCi/g - no action

2.
3,
4,

c.

PLAN
1.
2.

3.
4,
5.
6.
7.
8.
9.

View
Graph

10.
11.
3.

View

Graph

Runit
Map

Rad measurement (survey)
Excise soil
Re-survey
Excise soil
Etc: to level
Concurrent ~ burial sites
Move to Runit - radioactive

Dump nonradioactive
Stockpile & dispose (crater)

2,
bd.
c.

Runit vs Resources
Heterogeneous = uncertainty
Volume - 80% or 63,000 cu yd vs 16,000 cu yd.

£.

reasonable expenditure of resources.
Recommend - method

,

size of effort

Fig/Quince area

OPEN DISCUSSION
a, Can we get definition

b.

c,.

Validity

Uncertainty > uncertainty
Can we get better definition of scope of work - within

DATA REVIEW
a.
Pace data
b.
EPA data
c.
NVO - 140 data
d.
Crater area
e.
"Clean area"

f.
5.

Classify debris

Clear brush

PROBLEM

d.
e.

4.

Radioactive debris
Burial site(s)
>400 pCi/g - mandatory (NBLB)

How (method (s))

Cost (Resources)

Select target paragraph3