3.17

SAFETY

Preparation. The Task Group 7.1 Administrative Plan for Operation
Hardtack established safety as a command responsibility and assigned a
Safety Advisor to Headquarters TG 7.1 for consultation on all matters per-

taining to accident prevention.
The Safety Advisor spoke to the Project Officers at a meeting in Albu-

querque in the fall of 1957 on the subject of "Safety Problems in the Forward
Area." Individual Project meetings held in Los Alamos in December 1957
were attended by members of the safety group to acquaint personnel with the

safety problems associated with the projects and recommend safe practices.
Two papers on health and safety considerations at the Eniwetok Proving
Ground were distributed to all personnel before their arrival at the test site.
Close liaison was maintained with J-4 on the packaging, shipping, han-

dling, and storage of hazardous materials and devices.

Two members of the

group attended a JTF 7 meeting held in San Diego in January 1958 on the’
problems associated with handling and shipping devices from their point of
origin to the test site. The Safety Advisor prepared a paper on safety prob-

lems and emergency action connected with the test devices.

This paper was

made the Safety Annex to the JTF 7 Shipping Plan.
In consultation with J-6, plans and specifications for test site facilities -~
and structures were examined for safety considerations.

Personnel.

The staff function of Safety Advisor to the Commander,

Task Group 7.1, was assigned to the Safety Director of the Los Alamos
Scientific Laboratory. In addition, the post was filled by five Staff Members
from LASL. Safety Advisors were present at Bikini and Eniwetok Atolls
from February 16 to the end of the operation, and at Johnston Island from
June 29 to August 19, 1958.
Operations. The movement of all hazardous materials, including test
devices, into and out of the EPG and between and within atolls was carried
out with procedures advised upon by the Safety Advisor, who was in attendance at one stage or another during such movements.
Project stations, towers, tower elevators and stations, zero point barges,
facilities and equipment, boats and vehicles, and recreational activities were

surveyed and examined for safety.

Problems of mutual interest were coor-

dinated with safety personnel of other Task Groups.
Accident reports and forms were completed on all disabling and serious

injuries.

Forms were distributed to the home offices of the employees in-

volved and to the Bureau of Employee Compensation at its office in Honolulu,

T. H.

Safety information was published in the Information Bulletins issued by
the Adjutant General's office, J-1.
In connection with test rocket firings from Johnston Island, the Safety
Officer was appointed Rocket Range Safety Officer to coordinate safety mat-

ters with the JTF 7 Control Point.

Procedures were developed to assure

the safety of personnel involved in test rocket firings; danger zones and
water, air, and ground exclusion areas were established; and warning signals
were installed to alert the general population. Routine inspections of scientific stations were carried out, and special attention was given to small boat
activities and personnel evacuation.