POST -GO

PROCUREMENT Completed. The dish antenna, pedestal, control van, and
transmitter equipment will be shipped to Johnston Atoll by TC. To meet the
FOD the antenna dish and pedestal must be delivered at Johnston Island no
later than GO+48 days.
CONSTRUCTION The TC furnished antenna dish and pedestal will be erected
on the existing foundation. The TC furnished control van will be located on
the stabilized area along the east side of the transmitter building. TC furnished switchgear will be installed in the transmitter building. TC will also
furnish and install all power and signal cable required between the transmitter
building and the dish antenna.

*Includes Procurement