Since the skip hoist operated outside of the 200 foot tower and
passed up through an opening in a platform at the top level, minor
changes were required on the skip cab (platform), As it did not have
to open a trap door at the top level, the framing above the railing
level was removed. Because the skip was loaded at one end at ground
level and at one side at the top level, it was necessary to make the
railing on one side removable (the removable end portion used for
300 foot towers was not changed). These changes on the skip cab were
necessarily made in the field at the time of installing on the 200

foot tower, because the cab had been shipped with the 300 foot towers
before the 200 foot towers were conceived.

The portable hand-operated winches and cable from the 300 foot
tower cab, were used on the 200 foot tower, but because of structural
design of the tower house, the supports for the winches, cable, and
sheaves had to be of a different design, The winch supports were
mounted on the tower house structural members instead of on the Aframe as on the 300 foot tower. Figure 5.11-7 shows the main hoist
sheave assembly and cable arrangement for a 200 foot Tower.
A 7+ ton single I-beam type traveling crane was provided for each
200 foot tower. The crane was equipped with a 2-speed electric hoist
with gear type trolley. Hoisting speeds were 24 fpm and 10 fpm on the

total lift of 17 feet for the full height towers and total lift of 36
feet for the 25 foot mock-up section of the tower which was installed

at Los Alamos. Proposals were received from three crane mamifacturers
and analyzed. The acceptance of the low bid was recommended on May

24, 1950,

In a phone conversation on May 31, 1950, J-Division requested

H & N to design a detachable main hoist platform (or pallet) for

lifting freight from the ground to the tower house, using the main
hoist. At this point the pallet would be transferred to the 74 ton
traveling crane, to be moved to any desired location in the tower
house. H & N prepared a sketch showing a platform camposed of a

structural channel rectangular frame and covered with ¢ inch plate
with a 6 inch high toe plate on all four sides. The platform was

lifted by a wire rope sling attached to each corner and was provided
with double sets of roller guides on opposite sides of the platform
framing. The roller guides were to operate along the main hoist T-

guide rails and were spaced approximately 1 foot apart vertically.
Because eccentric loading of the platform was possible, the double-

roller guides were changed to single-roller guides. Also, the platform was provided with pull-out legs on each corner, so that the platform could rest on the floor of the tower house while it was being
transferred from the main hoist to the bridge crane. To comply with

this request, a new drawing (3G-5445) was made, using 6 inch pipe and

7 inch channels for the platform framing, single-roller guide assem
blies, and lifting cables at each corner of the platform. The pullout legs were of 5 inch pipe and made to telescope into the 6 inch

pipe.

The platforms were fabricated according to this drawing. Figure

5.11-8 shows a main hoist pallet platform for a 200 foot Tower, and
Figure 5.11-9 shows a complete perspective of a 200 foot Tower.

5-146

Select target paragraph3