SECTION 7
MISCELLANEOUS METAL WORK
7-Ol.
SCOPE:
The work covered by this section of the
specification consists of furnishing all labor, materials,

equipment, and transportation required to complete the
miscellaneous metal work as indicated on the drawings or
required for the work,

7-02. CODES:
The provisions of the following codes
and specifications shail govern the work insofar as
these provisions are applicable:
a.

American Institute of Steel Construction

publications (latest revision).
1.

Code of Standard Practice for Steel

Buildings and Bridges.

2.
Specification for Design, Fabrication
and Erection of Structural Steel for Buildings.

b.

edition).

American Welding Society Code (latest

1.

Construction.

Are and Gas Welding in Building

7-03.

INSPECTION AND TESTS:

7-04.

PAINTING:

Mill inspection and

tests will be waived if certified mill test reports
accompany deliverles and all heat marks are legible.

Refer to paragraph "C", sub 4 of

Section 10 on Painting.
Paint shall be applied only
to thoroughly dry surfaces and coverages shall be
even, full, and without runs or sags.

7-05.
GENERAL:
Supplementary parts necessary to
complete each item, though such work is not definitely

shown or specified,

shall be incluced.

Standard

commercial products which meet the general requirements
of the drawings and specifications and vary only in

non-essential detail will be acceptable,

the approval of the Contractor,

7-06.

GUARD BARS:

subject to

Shall be provided for openings

in locations shown and as detailed.