SERIES SCHEDULE
-2-

4 days survey Utirik
2 days survey Taka

(includes packing and travel)

_i day travel to Kwajalein

FERRERaT

24 DAYS
Crew change at Kwajalein.

SERIES
1 day travel to Aijluk
6 days survey Ailuk
1/2 day pack and depart for Mejit
1 day survey Mejit

1 day pack and depart for Jemo
1 day survey Jemo

1/3 day pack and depart for Likiep
7 gays survey Likiep

2 days pack and depart for Ujelang (2 days travel)
S days survey Ujelang

1 day pack and depart for Enewetak (16 hrs. travel)

__. SURVEY COMPLETE
26 DAYS

27 1ST SERIES
24 2ND SERIES

26 3RD SERIES
77 TOTAL TIME REQUIRED FOR TECHNICAL SURVEY