CHAPTER I SECTION 1 VOL, Il BOOK 6 transports the following to Elmer: mess hall equipment, reefers and ice machines (two trailers), distillation units and boiler (two trailers), beds and mattresses (one trailer), M-Boat with one fuel truck, one mechanic and one electrician leaves for servicing of generators on islands from Elmer to Janet inclusive. A DUKW with one mechanic and electrician leaves to service generators from Alice to Irene inclusive. 0800 T-Boat, Yvonne to Elmer, for removal of fresh and salt water tanks, 1200 CTG 132.1 assumes security responsibility for all islands in Atoll one crane and one lowboy. other than Fred. the USS ESTES. 1300 1500 CJTF 132 and CTG 132.1 open Command Post aboard T-Boat departs Yvonne for Elmer with vehicles and NRLK transpor- tainer. Last "dry run" of timing signals to be completed. One Dewar to be loaded on USNS PENDLETON from Elmer, Janet telephone operator to be evacuated, EE-8 telephone to be installed in Station 850 and connected to Elmer. Switchboard to be removed. 1600 LCM Elmer to Yvonne, Gene, and MSTS SHANKS (Evacuation Boat). 1800 Task Group Commanders report status of evacuation to CJTF with details of elements still to be evacuated. 1900 Yvonne telephone switchboard closes. Switchboard to be left in place. Yvonne telephone operator to be evacuated, required pairs are crossconnected on switchboard. Power plant to be secured. 1930 LCM Elmer to MSTS COLLINS (Evacuation Boat). LCM Elmer to USS RENDOVA and MSTS COLLINS (Evacuation Boat). LCVP Elmer to USS ESTES (Evacuation Boat), Post office on Elmer closes this date at regular closing time. distribution of mail. ship for delivery. 2130 Last All undistributed mail will be transferred aboard Detailed command conference: MIKE execute order confirmed. M -1 Day User Hour Item 6.2 0600 LCM and LSU with crane depart Elmer for raft Stations 621.01 - 621.06 with two men and five tons cargo. One man 6-3