VOL. Il
BOOK 5

CHAPTER
Iv
SECTIONS 17.18

placed in one tent and provided with 110 volts of single-phase power and a con-

venience outlet.

Lights were furnished and installed in both tents.

Two laborers

were furnished to assist in uncrating the project's equipment, and a forklift and
Operator were provided to move material in the AEC Compound.

Material

was furnished for the making of 140 wooden stakes measuring 2'' x 2" x 18"
long, for mounting the "blue boxes''. One laborer was provided for three days
to assist in installing Project 5.4b instruments off-island.

A Holmes & Narver crew with equipment placed a Project 5.4b instrument

weighing 300 lbs. in the base of Station 541.33, located at Site Mack. Following
K-Day, this instrument was removed. Beginning on K +2 Day, four Holmes
& Narver laborers recovered test equipment from the Station 541] series for
four days.

Two M-Boats and crews were provided to Project 5.4b for the

purpose of moving its equipment from Site Nancy, Pearl, Olive, Ruby, Sally,
Ursula, Vera, Wilma, Yvonne, Bruce and David.
At Sites Alice, Belle, Clara, and Irene, Holmes & Narver assistance was

also required to help remove the scientific equipment, and an M.-Boat and crew
were provided to assist in recovering scientific equipment from Sites Janet,

Kate, Lucy, and Mary.
SECTION 18.

Man hours expended, 834.

PROGRAM 6

PROJECT 6.1.

Sundry services supplied to this project included erection

on Sites Gene and Yvonne of two 8-man tents with wooden floors, overhead

lights and power outlets on each side and at the back, and work benches and
not lockers. Support labor for the splicing and laying of Sandia's cable was
furnished from late July to late October. A wooden rack, measured to fit on
a 6 X 6 truck, was constructed to hold reels of cable for laying. Lengths of
1-1/4" pipe were fitted in the rack to support the cable reels.
stands were provided at Site Gene.

Two similar

Two carpenters were supplied during the greater part of the operation to
assist the project in assembling and installing shock mounts, recording cabinets,

shelves, and benches in the Sandia recording shelters.

An 8-man tent with wooden floor, overhead lights and two 110 volt duplex
outlets on each side and along the rear wall of the tent, was erected in the
AEC Compound adjacent to the south side of Bldg. 231. In Bldg. 231, plywood
inserts were installed in the racks over the benches. The services of a forklift
and operator were required at the AEC Compound on several occasions during
the operation.

Seventeen generators were repaired by welding; 12 scaffold hangers were
constructed from one-inch steel bars and boards for the scaffolds were furn-

ished, measuring 12" x 2" x 12'; 30 cable run brackets were constructed from

5-19

Select target paragraph3