VOL. II BOOK 5 CHAPTER Il COAXIAL CABLE LAYING COAXIAL CABLE Laying of the coaxial cable at the Gene chain was a feature of Project 2. la; at Yvonne it was a feature of Project 2.1 b. These projects were supported by furnishing material, equipment, and personnel to NRLK. The AEC Work Orders covering these two features requested winches, power to pull the cable, working platforms, the construction of acid tanks for cleaning the cable, including a twoinch water line to the acid tank, and the stabilization of a parking area for trailers. A D-4 caterpillar tractor was provided for pulling the coaxial cable. © The supporting labor furnished by Holmes & Narverin addition to equipment operators, included three electricians, one telephone cable splicer, four la- borers and one carpenter. A total of 5638.5 man hours were required for this support. 5-3