Ee, JTF-7 letter J4/600.6, dated 14 March 1956, from the Commander of Joint Task Force Seven to the Manager of the AEC Albuquerque Operations Office. JTF-7 letter J4/300.1, dated 27 December 1957, from the Assistant Adjutant General to the Manager of the AEC Albuquerque Operations Office. The criteria reflecting AEC requirements were obtained during a meeting between Holmes and Narver Project Engineers and the AEC Jobsite representatives at the Eniwetok Proving Ground from 28 October 1957 through 3 November 1957. The cost analysis submitted with this report have been made withrespect to each project individually. No attempt has been made to establish priorities of construction or to formulate a budget. Cost estimates submitted in the June 1956 report have been re-evaluated on the basis of expected construction costs during FY 62 and are compatible with the construction standards of projects submitted im this report.