ROBERT E, MILLER

3

ABANDONED EQUIPMENT.

7/31/69

IN ADDITION, APPROXIMATELY 1000 TONS OF CONCRETE RUBBLE

WERE USED AS RIP-RAP ON BEACH ADJACENT TO OLD CAMP.

CONCRETE BUNKERS WERE

:

STRIPPED OF ALL EXPOSED METAL AND CLEANED OUT; BERMS AND CORAL FILL REMOVED

!

AND USED AS FILL OVER SCRAP PITS AND LOW AREAS,

CLEARED AREAS WERE GRADED,

THE BEACHES WERE CLEARED OF SCRAP METAL INCLUDING OLD PONTOONS, EQUIPMENT,
BARGES AND BOATS.

SALVAGEABLE BUILDINGS WERE CLEANED OUT AND LEFT INTACT.

A

STRIP THE LENGTH OF THE ISLAND AND ALONG THE LAGOON BEACH WAS CLEARED FOR
BUILDING SITES.
5S.

WORK COMMENCED OW THE SOUTHERN COMPLEX OF ISLANDS ON JUNE 12 WITH FIRST

WORK AT -PETER-OBOE IN THE OLD CAMP AREA WITH DEMOLITION OF OLD WOODEN STRUCTURES,
CONCRETE SLABS, FOOTINGS AND FOUNDATIONS; REMOVAL OF TOWER ON TARE, CONCRETE
BUNKERS WERE STRIPPED OF EXPOSED METAL AND CLEANED, CASLE BERMS LEVELED,
DISPOSED BY BURIAL SCRAP METAL AND DEBRIS, CONCRETE RUBBLE USED AS FILL FOR
SEAWALL, SCRAP ON REEF AND ALONG BEACH PICKED UP, CORAL FILL REMOVED FROM
BUNKERS AND USED AS FILL IN LOW AREA ON ROGER,

APPROXIMATELY 50 TONS OF "HOT”

MATERIAL WKE DISPOSED OF AT SEA BY MARINE BURIAL.
18 SCHEDULED FOR COMPLETION MID-AUGUST,
JULY 15.

WORK IN THE SOUTHERN COMPLEX

WILLIAM ISLAND WAS CLEARED JUNE 28 -

WORK INCLUDED REMOVAL OF TOWER AND ANCHOR BLOCKS, EXPOSED METAL FROM

BUNKER, BARGE ON BEACH, TERMINAL VAULT AND BURIAL IN PIT,
USED TO BACKFILL OVER SCRAP PIT AND TO LEVEL LOW AREAS,
COMMENCED JULY 18 AND WAS COMPLETED JULY 25.

FILL OVER BUNKER WAS
CLEANUP ON UNCLE

WORK INCLUDED CLEANUP OF BUNKERS,

SCRAP ON REEF AND ISLAND INCLUDING THE REMAINS OF AN OLD AIRCRAFT, DEMOLITION
OF CONCRETE STATIONS, BURIAL OF SCRAP AND BACKFILL WITH CORAL FROM COVER

a

OVER BUNKER,