OPERATIONS PLAN
LLL RADIOECOLOGY- AND DOSE ASSESSMENT
PROGRAM AT ENEWETAK ATOLL
-3-

Travel Orders and MAC reservations for the appropriate

MAC flights.

Coordination of this operations plan with all concerned
parties prior to the arrival of LLL at Enewetak and
coordination of any changes which occur during the mission.
Enewetak Base Support required:
1.

Enough food for seven people for two weeks to be purchased
from storage for use at Enjebi.
Use of the backhoe, multi-hoe, two dump trucks, three 4x4
personnel carriers, and the two mules.
Operational readiness of the LLL water truck filied with
3000-5000 gallons of water.

Use of the other 12.5 KW generator for use as backup for the
trailer at Enjebi.
All gear and equipment shipped to Enewetak ready to be
transported to Enjebi or transported previous to November 30.
Assistance from H&N man designated to support LLL Garden
Project, 25% of his time.
Full time support for this
individual during the 2 week period would be desirable if
it can be arranged.
Aqua sport boat availability and assistance with putting it
in the water.

Mike boat transportation as follows:
a.

One trip prior to November 30 to transport full water
truck, diesel fuel tanks to fill 500 gal. tank at
Enjebi and 200 gal. in drums and 200 gal. of gasoline
in drums.

b.

One trip each day on December 1 and December 2 to transport
remaining LLL equipment and supplies.
If two trips
cannot haul all of the LLL equipment a third trip will
be required.

c.

One trip may be required at some point during the twoweek period for resupply of food, water or fuel, or some
other unforeseen requirement.