Considerable difficulty was experienced by the project in placing anchored FFP’s in the array.
Although the anchoring system had been succesSfully tested in the Umbrella area several times
prior to final placement, only 16 out of 36 anchored FFP’s placed the afternoon of 6 June were
Still in position the following morning. The high percentage of failure was probably due to short
choppy seas that had blown up the day before in the Umbrella area. The project redesigned and
remade 36 new anchored FFP’s, improvising somewhat froin depleted stocks. On the morning
of D-1 day, the new anchored FFP’s were placed in the array and remained in position until the
shot. After the final test Signal at 1340 on D—-1, the project armed all coracies, using the USS
Munsee outside the lagoon and the AVR inside. Al} stations except two were armed and ready
by 1800 on D-1. Two of the coracles had pretripped during placement and were therefore removed from their moors, re-armed during the night, and replaced at their stations the morning
of D-day.
D-day activities were considerably modified from those of Wahoo. Instead of photomosaic
mapping, all preshot positions were obtained by M-33 radar on Eniwetok Island, which ranged
on a spotting helicopter as it hovered over a given station. Postshot positions were obtained

Similarly with Mark 25 fire-control radar aboard the USS Boxer (LPH-4) ranging on the Marine

helicopters performing FFP recovery. Also, because of the possibility that a large number of
coracies would break their moors and drift onto the reef, the project had two recovery teams
Standing by during the shot; each team consisted of one LCU with a crane aboard, one LCM, and
one DUKW with A-frame carried aboard the LCU. All project recovery was coordinated by Task

Group 7.3 from the CIC aboard the USS Boxer.

At H-2 hours, 14 FFP’s were dropped by the Task Group 7.4 helicopter outside the lagoon

along previously planned drop lines (Section A.5).
ery operation moved aboard the Boxer.

At H~1 hour, project control of the recov-

The two lagoon recovery teams, the AVR, and the USS

Munsee with another LCM remained near the Boxer during the shot. At H+30 minutes, two
Marine helicopters departed the Boxer to recover the free-floating FFP’s outside the lagoon;
meanwhile, a second drop of self-anchoring FFP’s was made inside the lagoon from an SA-16.

Also, two FS’s were recovered from the target array by the Task Group 7.4 helicopter and returned to Parry Island for Cl™ analysis and beta-gamma decay measurements. ,

Recovery of the free-floating FFP’s outside the lagoon proceeded rapidly and was completed
at H+1'4 hours. The two Marine helicopters then moved inside the lagoon and continued FFP

recovery.

Between H+1 and H+ 1% hours, project crews performed early recovery of samples

from the DD-474, DD-592, and DD-593, all samples being processed through the SRC. All ship

Samples, together with aliquots of all sample solutions used in early chemistry, were placed
aboard the H+6 hour flyaway. Also at about H+ uy hours, the two Special recovery teams and
the AVR moved into the array to check for drifting coracles and assist in FFP recovery. No
coracles had broken loose from their moors; however, seven had been overturned by the detonation.
At H+ 3% hours, recovery of the coracles began with the USS Munsee operating outside the
lagoon, one LCU and LCM team in the north section of the array, and the second LCU and LCM
team in the south section. The AVR and the two Marine helicopters continued FFP search and

recovery, completing this operation at about H+5 hours. By H+7 hours all coracles except
the two reef stations had been recovered, and 63 FFP’s had been retrieved. (Task Group 7.3’s

efficient and effective recovery unquestionably increased the value of the data obtained on Shot
Umbrella and is greatly appreciated by the project.) Coracles were returned to the BWA, where
pulling and counting of IC trays started immediately and continued throughout the night.
On D+1 day, the USS Munsee, assisted by an LCM, recovered the two coracles on the atoll
reef and completely cleared the entire Umbrella array of remaining mooring components. Also
on that morning, the project performed a complete recovery and survey of all target ships.
Complete stripping of all coracles was started at the BWA, and again all samples were processed through the SRC to assure both proper logging of data and contamination control. By
1430 of that day the IC count on all 24 sets of trays had been completed, and the trays were
ready for air shipment to NRDL for further analysis.

54

-

Select target paragraph3