CHAPTERII, SECTION 1
of cable pairs and reduced the size requirements
for the vaults.
Comparison of Engineering Design with
Previous Operations
A new method for the design of non-ex-

pendable, blast-resistant structures was adopted

for Operation HARDTACK.Prior to Operation
HARDTACK, non-expendable structures were
designed on the basis of allowable stresses for
wind load: i. e., for allowable static load stresses
increased by one-third. The new method applied principles as outlined in the ASCE publication, “An Engineering Approach to BlastResistant Design.” The system was basically an
“ultimate design” method using considerably
higher allowable stresses than for wind load. The

net effect of the new design method wasto reduce re-inforcing steel sectional areas and wall
and slab thickness. By reason of this effect and
the lack of experimental field data, a factor of
safety of two was usually applied, but depending
on the nature of the structure size and the test
evaluation importance for some extremely high

psi loading, the factor of safety was reduced in
some cases to as low as 1.5. It is anticipated that
Operation HARDTACK post-shot damage inspection reports will supply valuable information to the Design Engineers to alleviate questionable design considerations and will lead to
more certain and economical blast-resistant design method standards.

The scope of engineering design for Operation HARDTACK was more extensive in quantity and variety than for past Operations. This
is attested in part by the greater numberof drawings prepared. PAC Construction design require-

ments resulted in the preparation of design drawings for the construction of many more categories

of permanent base facilities, several of which

were extraordinarily large and unusual. The design program for Scientific and Expendable Construction required less complex engineering analysis and planning than the PAC program. In
addition, experience gained from previous Operations and the systematic use of the new blast
load design method contributed to the moreeffective and expeditious scientific design. The fact
that the extent of the design detail and the number of design drawings were greater can be at-

tributed to the greater numberof test-shots for

Operation HARDTACK as compared to REDWING; preparations for participation of the
ABMA missile project at Site How which was
subsequently moved to Johnston Island; and
the considerable number of facilities developed

at Site Nan.

Operation HARDTACK notably excluded

steel tower zero stations but generally supplanted
this shot vehicle with modified U.S. Army BC-

type Deck Cargo Barges and LCU hulls. The

development of Shot Barge plans for LASL and

UCRL required considerable plan details and

detail design for four barge types. New or
modified major Scientific Stations designed of
re-inforced concrete surpassed the extent of overall detail design requirements for other recent
Operations because of the greater number of
new stations designed in this category. The development of re-inforced concrete structures at
Eniwetok Atoll was predominant on Sites
Yvonne, Gene, Helen, Irene, and Janet and at

Bikini Atoll on Sites Peter, Sugar, Tare, How,
Dog, Charlie, and George.
Liaison With Jobsite

The principal liaison between Home Office
and Jobsite Engineering was accomplished by
Engineering Work Orders and Contract Authorizations. The Engineering Work Order copies to
Jobsite were not only a direct means of conveying detailed information pertaining to the scope
of design planning performed by Home Oftice
Engineering but in some cases assigned engineering action to be accomplished by Jobsite Engineering. The Contract Authorization documents
were mainly to authorize Jobsite camp maintenance and operations and miscellaneous construction projects for which action was requested
of Jobsite Engineering by the AEC Chief, Eniwetok Branch Office. They also served to keep
Home Office Engineering informed of the scope
of Jobsite Engineering action that might be cor-

related with Engineering Work Orders. The main

line of liaison of correspondence was teletype

messages. This medium was used extensively by
the Chief Project Engineer and the Resident
Engineer to expedite information requests, clarification of details, status of work, and plan
changes. TDYvisits were made by the Engineer-

ing personnel, as required, to correlate Home

Office and Jobsite efforts.

Liaison With Users

Design criteria were obtained from the Users
by means of letters, often with plan sketch descriptions of required new facilities or modifications to existing facilities. All criteria letters
requiring design and engineering action were
documented by the Project Engineers with the
issuance of Engineering Work Orders for each
facility project. The Project Engineers assigned
to the various Users in a liaison capacity effectively expedited their respective design program

from original criteria to issuance of final approved drawings by continuous contact with the
various User representatives to discuss their de-

sign and engineering requirements. In this manner, new design planning was anticipated in advance of receipt of first criteria letters; status of
current design projects became known; and design completion date requirements were planned.
Action was then initiated for field tests or surPage 47

Select target paragraph3