CHAPTER II, SECTION 1
designed to resist 0.75 psi side-on and 1.5 psi
reflected overpressures without temporary shoring or bracing. Dependable air-conditioning and
power supply were the most important design ©
feature considerations to ensure protection of
the electronic components of the computer from

corrosive action and equipment shut-down due
to powerfailure.

sea-wall problem was to provide a design that
would permit construction during all tide stages
on the ocean reef and was resolved by using
precast concrete wall sections between vertical
steel H-piles.
Operational requirements of the submarine

cable telephone and signal systems at Eniwetok

and Bikini Atolls, together with a complete ex-

amination of all existing cables made at Job-

site, provided design criteria for the analysis of
each system to determine the extent of rehabili-

tation and new installations necessary to bring
the systems up to the stipulated HARDTACK
capability. The new criteria included desirability
of

separating

the communication and signal

systems, both in cables and at land terminals,
for safety and maintenance reasons. In addition,

new signal requirements included thestipulation
that an adequate number of pairs be provided

to accomplish the simultaneous firing of three
separate events at each atoll, with a minimum
of 50 per cent of the allocated pairs as back-up.
Continuity and insulation-resistant tests
were conducted on 2,112,800 feet of existing
cables, as follows:
5 pr. #14 oe.

549,800 feet

5 pr. #19 0.

122,400 feet

16 pr. #19 1,417,100 feet
OL pr. #19 2.

23,500 feet

Total... 2,112,800 feet
Based on the results of these tests and the
known operational requirements, an engineering

(Neg. No. W-V-241-7)

Figure No. 2-4. Typical Submarine Cable
Vault — 50% Complete.

The Multi-story Barracks, Buildings Nos.

456, 457, 459, and 460 constructed at Site Elmer,

were the first two-story (128-man) barracks
buildings to be built at EPG. An extensive design and cost study was prepared to determine
the most feasible and economical design. The
results of the study andlater investigations determined the selection of a final design having
precast concrete first-story frame bents, precast

flat slab second floor, all-aluminum second-story

bents, and corrugated aluminum roofing and
siding, This was the first use of precast concrete

as an element of permanent building construction at EPG.

The Airstrip Extension and Warm-up Apron

at Site Fred was the largest FY 1958 PAC construction project. Design problems included de-

termination of asphaltic concrete and unre-inforced portland cement concrete pavement design
sections, design of a 855-foot-long concrete seawall, and newairfield lighting systems. The

analysis was made and a report was submitted
to the AEC containing proposals for modifications and additions to the existing cable plants.

Permission to use approximately 400,000 feet
of 16 pair +19-gauge submarine cable in warehouse stock at Jobsite, and authority to procure
an additional 1,000,000 feet of 26 pair +19gauge submarine cable were requested. Upon

approval, purchase specifications for the 26-pair
219-gauge submarine cable were prepared and
procurement wasinitiated.
Two types of submarine cable terminating
vaults were designed, predicated on anticipated
overpressures at the individual sites. Each vault
contained two separate compartments, with
terminating facilities in one for the telephone
pairs and in the otherfor signal pairs. To ensure
operation of the communications and signal
systems immediately after each event, the vaults

were designed as a below-grade structure with
a waterproof hinged roof. Waterproof terminal
boxes were positioned just below the covers in
a horizontal configuration, mounted on hinged

frames to allow their movement to an upright
position above grade when the covers were open.

This facilitated the connecting and checking

Page 45

Select target paragraph3