CHAPTER |, SECTION 1
Of the difficulties encountered during the
construction build-up, the logistic problem was
one of major importance. In order to maintain
the anticipated construction schedule, it was

necessary to transship all existing equipment
and materials from Site How to Johnston Island.
Procurement of additional scientific equipment

an accelerated pace until the completion of all
Scientific Stations on 7 July.
It was determined rather late in the planning stages that a 500-kw generator was required
to fulfill the island’s power needs. This presented

a tremendous problem, in view of the fact that

and materials from Honolulu and the mainland

generators of this capacity have a long procure-

in most instances by MATS and commercial
air freight to Honolulu for transshipment to
Johnston Island. During the construction period,
a total of 35,194 measurement tons (5580 long

ville, R. I., for the loan of a 500-kw portable
generator. Also, it was found necessary to borrow

was also necessary, with shipments being made

tons) was received at Johnston Island by surface

craft and 2,193,955 pounds by air.

The entry of H&N into activities at Johnston Island posed additional problems from a

security standpoint. The key factor was that
any indication of AEC or JTF-7. interest in,

ment lead-time. To overcome this obstacle negotiations were concluded with the Navy at Davis-

from the Navy at Pearl Harbor seven pieces of
heavy equipment valued at about $200,000. As

a result of these arrangements with the Navy,
critical items were obtained without disturbing

the logistic program at Eniwetok and Bikini
Atolls. No costs were incurred other than transportation and rehabilitation upon the return of
the equipment.

or occupancy of, Johnston Island in relation to
testing operations was initially classified as
Secret. This made it extremely difficult to re-

WEATHER AND RAD-SAFETY
STATIONS.

would arrive at Johnston Island on an uncleared
basis and, in addition, any indication of Johns-

Scientific Users keep constantly aware of the

cruit personnel, as the bulk of new employees

ton Island as the destination of materials procured for the test program would have compromised classified information. The problem was

resolved through conferences with the ALO Clas-

sification Division and Test Division officials

which resulted in an early declassification of
information pertaining to intended testing acti-

vities at Johnston Island. Based upon this de-

classification decision, permission was obtained

from the CJTF-7, through the ALO Test Division Security Officer, to use employees on an
uncleared or ‘‘GSR” basis indefinitely. This
factor also eliminated the security problem in

A successful test series requires that the

changing weather and radiological conditions;
therefore, it was considered essential to establish
new, and rehabilitate existing, Weather and Rad-

safety Stations at various atolls forming a ring
around the EPG. These atolls presented a diversity of climates, topography, marine andaircraft
landing conditions, and ownership. Although it
was the responsibility of the military services

to operate these stations, H&N was contractually
obligated to survey the sites and construct the
necessary

support

structures.

Construction

efforts with respect to the off-atoll weather and
rad-safety sites are covered in Chapter II, Sec-

connection with the procurement and shipping
of materials. Wherever possible, cleared employ-

tion 4, Expendable Construction. In many instances, it was necessary to accomplish this
assignment under adverse conditions seldom en-

able portion of the personnel requirements were
filled with new hires from Honolulu, on a “GSR”

Assistant Director, Test Division, AEC, ALOO,
that JTF-7 was planning to use the following

ees were transferred from Eniwetok and Bikini
Atolls to Johnston Island; however, a considerbasis. HEN established a TG’7.5 Pass and Badge

Office at Johnston Island to handle the control

and issuance of security badges, and security

requirements were handled in much the same
manner as they were at Eniwetok and Bikini
Atolls.

A 60-hour extended work week was necessitated during the construction phase to maintain an. accelerated construction schedule. Scien-

tific Station construction began on 2 May, and

by 9 May the lower section of the service tower
for Station J-6001 was set on its auxiliary pad
and tower erection was in progress. On the same
date the inside wall forms were set for Station
J-6002, and half of the re-inforcing steel bar was
in place. All major Scientific Stations were under
construction by 1 June, and work continued at

countered in a normal construction project.

Early in 1957 H&N was notified by the

sites for weather and rad-safety purposes during
Operation HARDTACK:

WEATHER
Tarawa
Kusaie
Kapingamarangi
Nauru
Rongerik
Utinik

RADSAFETY
Wotho
Ujelang
Rongelap

U.S.
WEATHER
BUREAU
Truk
Ponape

An interesting aspect of this program was
the land lease terms that were entered into be-

tween a negoviating team, composed of representatives of the AEC, the Trust Territories, and
H&N, and the owners of the various atolls. In
most of the atolls these arrangements were concluded with the native chiefs; however, in several

instances the negotiating team dealt with Cau-

Page 29

Select target paragraph3