CHAPTER II, SECTION 7

SECTION 7
CONSTRUCTION AND PLANNING
GENERAL.
The Construction and Planning Department functioned under the general supervision of
the Chief, Construction and Planning, who was
primarily responsible for the over-all coordination
between Home Office Engineering and Procurement and Jobsite Supply and Construction. In

addition, this Department was responsible for the
publication of various periodic and special reports; standardization of nomenclatures and the
publication of material stock lists; construction
equipment budgeting, planning, inspections, and
recommendations for procurement; Home Office

requisitioning; Stateside material and installed-

equipment inspections; and maintenanceof strict
contro! of all material and equipment shipments to Jobsite.

MATERIAL TAKE-OFF-SECTION.
To meet the construction schedule for Operation HARDTACK it was required that Advance Material Estimates (AME’s) be issued

by the Material Take-off Section prior to release of engineering drawings and the covering
Construction Bills of Material (CBM’s). This

enabled advance procurement action to be undertaken and in manycases resulted in the receipt

of material at Jobsite prior to the approval of

design drawings.

Information for the preparation of the
AME?’s was derived from an analysis of items
used during REDWING to determine the items
and quantities which might be considered standard in any given Operation. These were regarded
as stockpile items and were included on AME’s
as soon as the scope of the Operation was known.

of a combined PAC and Scientific CBM item
total of 3663 line items per month, as compared
with a total of 1564 line items for REDWING.

MATERIAL CONTROL SECTION.
Prior to the inception of procurement action
for Operation HARDTACK,a decisive change
was made in the method of maintaining data
pertinent to construction progress and scheduling. This was accomplished by revising the
Material Status Report used during Operation
REDWING in such a manner as to project

more realistic delivery dates of materials and
equipment. The current delivery information on
all major items of construction materials and
equipment was furnished to Jobsite daily by
the Material Status Report, which reflected all
changes of deliveries and estimated Jobsite arrival dates. This was supplemented by daily
teletype reports on all critical items which gave

Jobsite information for scheduling for an extremely tight construction program.

During the operational period, an Estimated
Operations Schedule was used which included
information relative to engineering, procurement, and construction progress pertinent to
all known Scientific Stations and supporting
facilities. This schedule was assembled and distributed to all interested parties, making it possible to coordinate and plan all phases of the
build-up program.
In comparision to REDWING, the allowable lead time for delivery to Jobsite for all

materials and equipment was reduced by ap-

proximately 40%, which required a constant

control of all shipments. As the Operation pro-

by Engineering to provide descriptions of equip-

gressed and User occupancy dates became critical, a daily review was made of all material and
equipment scheduled for water transportation
and, when necessary, diversions to air freight

therein were reviewed and used as a basis for

lead time, intensive expediting action was required throughout, and on various occasions
it was necessary to authorize premium pay-

Also, Advance Information Forms, designed

by the Material Take-off Section, were used

ment and material for which a need was known
to exist but for which the covering design drawings were not completed. Descriptions contained
issuing AME’s to authorize requisition action
in advance of the release of drawings and the
covering CBM’s for the pertinent facility.

To keep abreast of the HARDTACK scien-

tific program, CBM’s were completed at the
rate of 2332 line items per month, or approximately twice the rate required to complete the
REDWING scientific program. Additionally,
the Plant Acquisition and Construction (PAC)
program overlapped the Scientific portion of

HARDTACK which necessitated the issuance

were authorized. As a result of the reduced

ments for overtime on special fabricated items.

As a consequence, delays were held to a mini-

mum.

MATERIALS STANDARDS SECTION.
The period corresponding to Operation
HARDTACK wasone of increasing development
in materials standards. Previously, a comprehensive classification of all stores items and
commodities in constant use had been designed
and substantial progress had been made in comPage 323

Select target paragraph3