CHAPTER |, SECTION 1

(Neg. No. W-V-238-9)

Figure No. 1-5.

IBM Equipment Installation — Building 453 — Elmer.

plished by utilizing the existing vaults or constructing the new type.
~~
Under the supervision of the newly-created
Communications Division, communications facilities at EPG were greatly expanded in preparation for the forthcoming Operation. The Tropo-

was the IBM Building, an all-concrete structure
with suspended ceilings and, in one room, a
removable floor set on stringers on concrete

pedestals. This building, which contained an

air-conditioning system to provide both overhead

and under-floor circulation, was started in Octo-

spheric Scatter System and the Automatic Dial

ber 1957 and was available for occupancy on 10
February 1958. The largest new Scientific Sta-

service within Eniwetok Atoll and directly to

Janet, started in*September 1957 and completed

Exchange System provided automatic dialing
the switchboard on Site Nan in Bikini Atoll. A
military microwave system, a voice circuit to
Kwajalein, a carrier system, and a commercial

VHF System were also put into operation, thereby providing the more adequate and efficient
communications facilities demanded by HARDTACK requirements. The use of radio interference detection equipment provided better control and radio discipline of radio circuits than
was possible during REDWING.

By far the most complex building constructed under the PAC program for HARDTACK
Page 22

tion construction project was Station 1312 on

in April 1958. Besides the buildings and other
facilities contained in the over-all program, 788
Scientific Stations were required, of which 80

were considered of major size.

Concurrent with construction planning, personnel requisitions were prepared and recruiting
wasintensified to provide the personnel to Jobsite in the amounts necessary to accomplish
H&N’s mission. A peak of 3158 contract employees at Jobsite was reached on 9 April 1958. With

the arrival of other elements of the Task Force