CHAPTER II, SECTION 4

(Neg. No. W-882-11)

Figure No. 2-121.

George camp was started on 17 February

1958 as a 30-man beachhead serviced from a
marine craft, was occupied on 8 March 1958,

and wasclosed on 18 April 1958.

Johnston Island, the revised location for the

ABMA program, was selected when work was

halted on Site How on 10 April 1958. It was
initially occupied by H&N forces on 17 April
1958 and existing facilities were rehabilitated and

modified to accommodate an anticipated peak
population of 1200.

OFF-ATOLL PROJECTS.
As funds were provided, work was started
on the structure to be furnished the natives
being repatriated to Rongelap Atoll. The work
was planned to be accomplished in two phases.
Whenever possible, the precasting of concrete
and the prefabrication of structures was done

Site Janet Camp.

30 skilled men, depending upon the amount of
work to be accomplished. Construction parties
were augmented by Surveyors, an Inspector,

marine

operations

personnel,

Camp

Utility

Workers, and a First Aid Man. Native labor was

used at some sites. Equipment sent with each
party was standardized, usually consisting of
a bulldozer, an end-loader, a crawler-crane, forklifts, an air compressor, a welding machine, a
concrete mixer, dump, fuel, and pick-up trucks,
and, in some instances, a concrete-finishing ma-

chine. Both equipment and building materials
were loaded onto flat-bed trailers for quick offloading from LSD- and LST-type vessels. LCU
craft were used for off-loading from LSD’ vessels. The materials sent to each site varied with
the amount of work to be done, with building
prefabrication being done at Elmer or Nan,
whenever practicable.

at Site Elmer. Living quarters, a Dispensary,

Building materials for the new Utirik
Weather Station included 28,660 square feet

main facilities provided. On 20 June 1957 the
construction crew returned to Elmer; everything was in readiness for the repatriation of the

wood, 26,800 lineal feet of lumber, three 90-foot
antenna poles, and heavy lumber for the construction of a new water tower. Thirty construc-

a Council House, and water cisterns were the

of roofing and siding, 2200 square feet of ply-

Rongelapese.

tion workers and collateral personnel made up

Planning for Operation HARDTACK in-

the work party. Work was started on 16 October 1957 and was completed on 4 November

WING plus the construction of new Weather

party and turned over to the Air Force on 22
March 1958.

cluded the rehabilitation of the Weather and
Rad-safety Stations used in Operation RED-

Stations at Nauru, Truk, Utirik, and Ponape.
Preliminary surveys were made at each site,

‘ch provided “punch-lists” for the construction
aning. Construction at most sites was planned

» ve done in two phases, with most of the work
ing accomplished during the first phase. Sec-

ad phase work included minor clean-up and

ine activation of the stations.

Work parties were planned to consist of
an Assistant Superintendent and from 12 to
Page 228

1957; the station was activated by another work

A work party of 12 men departed Elmer
by LST for Ponape on 25 October 1957 to con-

struct a new Weather Station which consisted
of a single building utilizing local power. Twenty-

nine cubic yards of concrete were poured for
the building’s slab; the building itself was constructed of plywood and was given three coats
of paint, inside and out. Trust Territory officials
furnished a truck, sand, and gravel for the concrete slab and native laborers from the Trust

Select target paragraph3