Ne eel eT eeclairnityDeSine eo ne

.

CHAPTER 1
CONCLUSIONS
1.1

EPG logistics and the associated problems

of funding, advance procurementof longlead-time items, and delay in the preparation of

the performance of work on a “crash” basis and
a marked increase in the total cost of the
1.2

-v

le

ee

ee

ee

ee

ee

the definitive plans of construction resulted in

ee

oe

ee

PART IV, CHAPTERS 1 ond 2

program.

The expanded scope of the operation to
include Johnston Island contributed to a
serious shortage of experienced security personnel within TG 7.5.

1.3
’

The retention of responsibility for TG 7.5
radiological safety within
7.5 proved

successful in protecting the interests of the AEC

and should be continued during any future operation.

1.4

In view of the magnitude and successful
completion of Operation HARDTACK,
Phase I, it is concluded that all staff sections of
TG 7.5 and H&N accomplished an outstanding
job in the planning and execution of TG 7.5
operations.

CHAPTER 2
, RECOMMENDATIONS
The following recommendations are based
on the concept that future operations at EPG
will be comparable in scope to Operation RED-

WING and HARDTACK,PhaseI:

2.1

The concept of testing in the Pacific has
changed gradually over the past several
years, and it appears that even greater changes
may well be in prospect. Preliminary studies in-

dicate_that an appreciable_reduction_could be

madein_thepersonnelstrengthrequired to con-

duct an operation the magnitude of HARDTACK,
Phase I, under the revised concept of organization. Any appreciable reduction in personnel will

dividual projects approved by competent authority cognizant of the current MODUS OPERANDI and based on probable future scopes of
activity. Definitive p
would be reviewed in
a more orderly and realistic manner preliminary
to an authorization for construction on a normaltime basis.
2.5

Future budget planning should provide
for the bulk of permanent construction in
the fiscal year preceding the operational period.

This will result in a more economical and orderly ;
construction program.

Funds should be advanced for preliminary
and fina] engineering of expendable test
barracks, warehousing, etc. It is recommend
facilities as soon as the basic needs become
that a joint AEC-DOD review be made of the 7 known, even if a test series is not immediately
test organization structure and of the AEC-DOD
forseeable. Construction would be authorized
agreement, with particular regard to distribution
only after Scientific Users have demonstrated to
of supportservices between the twoagencies.
AEChigher authority that a specific device requires testing in the manner proposed. Many
2.2
Phasing of the use of EPG to one primary
preliminary and final plans probably would be
User (LASL, UCRL, or DOD) at any one
wasted; however, the savings realized in “nontime would tend to reduce further the total mancrash” construction programs would more than
power requirements and would result in stabilioffset added engineering costs due to discarded
zation of the Contractors’ work force to a lower
level. It is obvious that such a policy would not
Pp.

release drastically needed facilities, includin

only reduce scientific personnel strength but

would likewise reduce the strength of all supporting Task Groups. .
2.3.

TG 7.5 should be assigned complete responsibility for all radiologi
safety ».
support services at EPG during interim and
operational periods.
2.4

Funds for PAC construction should be
authorized on the basis of an APPROVED

projected 5-year long-range program, with in-

2.6

2.7

A substantial increase in investment in
the Contractor’s current-use stores inventory should be authorized, in view of the fact
that advance procurementof long-lead-time items
is highly important to the orderly and economical
consummation of a test program. Emphasis

should be placed on building up the inventory of
such items as coaxial cable, submarine cable, de-

humidification units, generators, PI&S building
sections, etc.

|

Select target paragraph3