PP HHH FI DFA AA dT AAA AIDIIIA IAI AAD SHH O SDS

cer

ert enh aetnaail
nt
eague
chilis rctue eee

4

PART Ill, CHAPTER 4
HARDTACK,Phase I, 2 were high altitude, 4
were surface ground shots, 1 was a balloon shot,
2 were underwater or sub-surface, and 26 were
detonated on floating zero stations.
4.3

The high altitude events required an
entirely new test facility at Site How in
Bikini Atoll for the Army Ballistics Missile
Agency. This new facility included the construction of 62 scientific stations, and was rushed to
completion in time for beneficial occupany only
through a “crash” program involving emergency
procurement and premium overtime payments.
At the end of March, 1958, when the facility
was substantially complete, it, became apparent
that the entire ABMA program should be moved
to Johnston Island for reasons of safety that
developed only as the program advanced. Once
the acquisition of Johnston Island from the
Pacific Air Force Command was achieved by
CJTF-Seven on 10 April 1958, the gigantic
task of moving the entire ABMAfacility from
Site How to its new location began. Construction
crews removed the ABMAfacility and re-erected
it at Johnston Island in record time. Construction at Johnston Island was completed on 15
July, two weeks ahead of schedule.

ENGINEERING
4.4

The engineering of test structures for
Operation HARDTACK involved the
design and construction of more than 350 scientific structures at various locations within the
EPG. UCRL requirements and criteria were in

the hands of the AEC Contractor by the end of

December, 1957, and those of LASL by the
middle of January, 1958. To expedite the necessary engineering design and planning requirements of the scientific program from initial
criteria to the release of approved plans for construction, H&N assigned Project Engineers from
its Los Angeles Office to provide liaison with
each of the major Scientific Users. At Jobsite,
the AEC Contractor created the position of
Technical Facilities Coordinator to execute new
and revised engineering design requirements and
to provide on-the-spot liaison between the Users
and the Contractor’s Jobsite Engineering Division. Headed by the Contractor’s Assistant
Engineering Manager and staffed with Project
Engineers, Design Engineers, and Design and
Senior Draftsmen from H&N’s Los Angeles
Office, this group stayed in force at EPG from
January until late April, 1958, at which time
the position of Technical Facilities Coordinator
was sustained by a Project Engineer until early
June. The Technical Facilities Group proved
very effective in the expeditious processing of —

User requirements and changesinitiated at EPG

and aided immeasurablyin the over-all construction effort. Drawings for Jobsite-designed test
facilities were approved by the Eniwetok Branch
engineering staff.

CONSTRUCTION
4.5

Expansion of the off-site Rad-Safe
Weather Station network called for the
construction or rehabilitation of facilities at
four other atolls in the Marshall Islands, Rongelap, Ujelang, Utirik, and Wotho and at Kapingamarangi and Kusaie Atolls in the Carolines;
and at Tarawa in the United Kingdom Trust
Territory of the Pacific, as well as at Nauru in
the Australian Trust Territory. Weather Sta-

tionswere also constructed at Truk and Ponape.

In most cases, materials were precut at Site
Elmer for assembly at the pertinent location.
4.6

The major scientific facilities at Eniwetok
Atoll were constructed at Sites Yvonne
and Janet and on the Gene-Helen-Irene complex.
These facilities were utilized in the detonation
of 18 LASL and 5 UCRL shots. Among the
major scientific structures were Station 91, a
300-foot photo tower on Site Elmer; Stations
1130, 1611, and 1612 on Site Yvonne, and
Stations 1212.01 and 1212.02 on the Gene-HelenIrene complex.
Station 1312, constructed for LASL and
EG&G, was the largest scientific structure built
for the Operation (see Fig. 3-5). It was designed
as a Recording Station for participation in the
DOGWOOD, PINE, OLIVE, OAK, ELDER,
YELLOWWOOD, TOBACCO, and WALNUT
events. For this station alone, a total structural
concrete pour of 3673 cubic yards was required.
The floor plan provided for five utility rooms,
connecting passageways, and an escape hatch
compartment to the outside and through the
roof.
Station 21, the GZ Station constructed for
LASL for the KOA event, consisted of two steel
tanks, one inside the other, and three sand-filled
boxes (see Fig. 3-6). The inner tank was 10 feet
in diameter and 11 feet high; the outer tank was
30 feet in diameter and more than 22 feet high
to maintain 10 feet of water above the inner tank.
Power was supplied by two 30-kw, 120/208-volt
motor generators.

47

Major scientific station construction at
Bikini Atoll was required on the OboePeter-Tare complex and at Site How. Station
2200, Site Sugar, was modified to add a generator room, and a 150-foot diagnostic tower was
constructed on top of the bunker and was des-

ignated as Station 2250. In conjunction with the

ABMA program,Stations 6001, a rocket firingpad andservice tower, and 6002, a control bunker, were constructed at Site How. In addition to
the two major facilities at Site How, there were
60 stations constructed for participation in the
two high altitude shots. When it was determined
that the ABMAfacilities would be reconstructed
at Johnston Island, all but 7 of the scientific
stations originally located on Bikini Atoll were _
Baa. AE

Select target paragraph3