Tuesday, August 22, 1978 2:30 PM Advisory Group members present: Templeton, Thompson, Wachholz Other participants: Bair, Gilbert, McClellan, Richmond, McCraw, Ray, Still, Sanchez, Bauchspies and staff Command Briefing by JTG staff. Command structure doesn't have direct control over operational activities. Must go through series commanders. Op plan 600-77 is controlling authority. Major tasks; I. Clean-up debris falls in 3 categories: Contaminated material to crater (red) Contaminated material to lagoon (yellow) Leave as is II. IIL. (green) Reduce surface contamination to 40-80-160 criteria. Special activities: Contaminated bunkers JTG is sealing some bunkers on Enjebi, rather than removing them (by sealing the entrance to the bunkers, they feel that they are "removing the hazard" such that it is "not a hazard"). Aomon crypt Pace crater (court order to restore contours) Plowing experiment IV. Island Status Some are ready for certification. All others in process of being cleaned-up--except one (Walt) A limiting factor in soil removal is transport across the lagoon. By 6/1/79 80K yds3 should be moved (originally estimated at 69K yds3) Accelerated schedule is maintained by Navy crews working 12-21 hrs/day and by the use of bulk loading techniques.