CHAPTER |, SECTIONS 1 and2
Precautionary measures against blast damage, wave action, and radioactive contamination

were taken as dictated by probable test yields.

However, after the initial shot (Bravo - Station
20) on 1 March 1954, all pre-test plans were

photographic and other recording stations had
to be abandoned or added to meet the requirements for the changed zero stations. Radioactive
contamination necessitated a new barge, Station

greatly modified.

1840.01, on a reef near How, in lieu of Station
1820.02.

The unexpected destruction of facilities and
the intensity of the residual radioactive contamination resulting from the Bravo detonation

The principal resultant problem to the
Contractor was the disposition of his forces,
particularly the abrupt shift from a land-based

necessitated changes in the test program.
Changes were made in the shot sequences; also,
Station 90 was moved to the Charlie crater;
Station 10 to the Flora crater; and a number of

to a ship-based operation at Bikini. The adapt-

ation was successfuly made for the limited
duration involved.

SECTION 2
CONCLUSIONS AND RECOMMENDATIONS
All of the foregoing narrative summary is
extracted from text treated in more complete
detail in following sections of this report.

The principal difficulties reported in OP-

ERATION CASTLE appear to have been related, directly or indirectly, to the scheduling
of the preoperational phases of construction. The

problems derive from the nature of the project.

The remoteness of the site, the lead time necessary for procurement and mobilization, the

difficulty of effective distribution of men and
equipment on widely dispersed areas, and trans-

port over the considerable water separation, all
contribute to a rather extended construction
period. Yet, in the earlier phases of the pre-

operational period, few criteria are firm except

the end date, which, being inflexible, demands

careful planning. Detailed schedules based on
firm scope are not possible until late in a pro-

gram when they were often too late for effectiveness, and early schedules tend to be frag-

mentary. However, experience in the problems

of GREENHOUSE and IVY has enabled the
Contractor increasingly to anticipate and evaluate missing factors, and thus make realistic

forecasts. The momentum ofscientific progress,
continuing to the moment of a test, makes most

of the resulting engineering and construction
problems inherent in the project. Although the
operational phase was changed in scope as a
result of the first detonation, the rapid solution

of the problems which followed indicated that

the existing procedural techniques and organizational set-up, were functional and flexible
enough to accommodate not only an orderly

progression in the operation, but also radical
changes in plans. Therefore, extended recommendations do not appear to be indicated.
Page 1-10

There

are a

few

refinements,

from the

Contractor’s standpoint, that might produce
some saving of time and money in other operations. Accordingly, the following is offered for
consideration in planning future test programs.
1. Experience gained during OPERATION
CASTLEindicates the need for more direct
control by the Contractor over contract employees in the matter of radiation exposure.
It is therefore believed desirable to establish
within Task Group 7.5 a non-military RadSafe unit which would be responsible for the
regulation of safety measures within the Task
Group.
2. In the development of design criteria, it is
believed that the Contractor’s personnel
should work in close proximity with the actual design groups at the University of Cali-

fornia Radiation Laboratory and Los Alamos
Scientific Laboratory in order to expedite the
development of criteria and, also, to help the
Scientific Groups formulate design require-

ments along lines which could result in simpli-

fication or standardization of construction
procedures and materials, thus resulting in
over-all savings in time and money.
3. As a means of reducing the number of personnel in the advance elements of the Task
Groups assigned to the Forward Area, con-

sideration might be given to instructing the
Contractor to assume additional responsibil-

ities in the handling, processing, andbilleting
of personnel; in warehousing of User’s equipment and supplies; and in other related functions at the Pacific Proving Ground which involve duplication of function, and for which
the Contractor is already established.

Select target paragraph3