4.1.4

Modification of Aircraft for Loeding

The lifting gear will be permanently installed on
the forward part of the aircraft, to avoid having to romove the access
plate in the engine cowling after contamination, Holes will be drilled

in the plate, the cable attached to the lifting pads, and bloomers installed around the cables to prevent contamination from getting into
the engine accessory section, Rigging will be mece up for each air=

creft, The cowling modification and fabrication of rigging will be
accomplished at NAS Alameda, (See Tab Cell for modification plans.)
4.1.5

Instruments

Fixed gamma recording instruments are being developed
by the NRDL Laboretory Instrumentation Branch, A directional gamma
probe is being developed to supplement the existing USNRDL beta probes,
See Annex E for details, Standard rediac sets will be used for survey
purposes,
4.2

Pre-Test Work on Transit ABLE and BAKER at USNRDL
4o2Rel

Location and Sceuring of Test Aircraft

An aircraft will be installed on #5 hatch on each ship

during sea trials in the Sean Francisco area, Loading and securing
arrangements for both sea shipment and test operations will be determinead

during these trials.

Three aircraft will be loaded on each ship for

transport to the test crea,

See Tab Cel for details,

Procedure for

loading and unloeding the aircraft will be checked out. These two air-~
craft will be installed at NAS Alameda by the NAS Alamede Supply Depcrte~
ment, (See Tab Cel for details.)

4.2.2 Tests During Sea Trials

ST. LOUIS FRC

A final check of the weshdown system will be made vith
the aircraft on #5 hatch, The wator coverage will be documented and thc
system will be modified if the water coverage needs improvement. The
location, connection and operation of three four-pi instruments will be
checked at this time with porsonnel of Projcct 6./f,

4.3

Post-Test Work on Transit ABLE end BAKER
Soe rollup,