P

exposed to alternate wetting and drying. All contract work was finished
on 13 March; the foundationswere then inspectedand accepted. (For
detailed plans of construction, see Drawings No. ‘+49, 52, and 53.)
Aomon-BiijiriCauseway. During the initial unloading and preparation period (1 January to 9 January), the C & GS survey party staked
out the center line on the Zero Tower - Timing Station line, the pile
line for a 30 foot wide causeway, and established elevations for the
pile cut-off line.

Clearing of an area on Biijiri for a borrow pit

was started by the contractor. @n 10 January unloading and general
preparations had progressed sufficientlyto permit driving of a test
pile. After 15 minutes of driting, the m38 pile ~d

penet~ted onlY

1* feet of sand and about 1 foot of an underlying xmck ledge. The test
pile was pulled, and preparationswere made to crack the ledge with
dynamite. This was successful,and 10 feet of penetration was obtatied
when pile driving was resumed, although driving continued to be hmd~
Blasting was not again required until the line of piles reached the
Aomon shore, where another rock ledge was encountered. WO*

continued

at an even peca; driving of 25 or 26 piles on two successive days, and
placing of tie rods and whalers, advancing the fill, the resetting the
pile frame on the third day. Actual progress, therefore, averaged only
17 piles per day. In an effort to speed the operation, which had been
hampered by high winds, it was decidedto advame the fill and haul
dirt from the borrow pit ●t night. W

haulingof fill nmterial was

carried on continuouslythroughout the construction;a total of 4500
cubic yards being used in the causeway, Another delay occured when it

Section,XVI
,
—

Select target paragraph3