ieee,
KAUAI, AEC-TRF
11024

SCIENTIFIC
Page 2

FY 1969
ENGINEERING

Drawings:

Completed.

JS 97-094-C2

PROCUREMENT

JS 97-094-Al

JS 97-080-E3 and E4

To be accomplished.

CONSTRUCTION To temporarily alleviate the presently overloaded commercial
system at the AEC-TRF, a 600 kw AEC furnished diesel generator will be shipped
from Damon Tract and will be installed on a concrete pier foundation south of the
main substation.
The main substation slab will be enlarged to accommodate three (3) new 250 kva,
120/208-4160 volt, single phase transformers. The generator will supply power
to the transformers and the transformers will supply power to a new 120/208
volt, 60 cycle, 3 phase power panel. Back up capability will be provided by tieing the two existing 75 kw generators into the substation's 600 amp automatic
transfer switch. The back up generators will be connected in parallel and their
output will be synchronized
A 30 x 30 x 14-ft. high prefabricated metal shelter will be installed over the
enlarged substation. The shelter will have metal roofing but will be opensided.
Chain link security fencing will enclose the new transformer portion of the substation.
The FY 69 work described above is a Maintenance and Operations project.

FY 1970
ENGINEERING

To be accomplished.

PROCUREMENT

To be accomplished.

CONSTRUCTION The major upgrading of the power system involving replacement of existing cables as needed, installation of new cables for planned
facilities and a main breaker panel cooling system will be provided.

POST -GO
ENGINEERING
PROCUREMENT

To be accomplished.
To be accomplished.

CONSTRUCTION The ultimate power requirement for the AEC-TRF is estimated at 1800 kw. Complete separation of scientific loads from utility loads

t1-25

VOLII

Select target paragraph3