ieee, KAUAI, AEC-TRF 11024 SCIENTIFIC Page 2 FY 1969 ENGINEERING Drawings: Completed. JS 97-094-C2 PROCUREMENT JS 97-094-Al JS 97-080-E3 and E4 To be accomplished. CONSTRUCTION To temporarily alleviate the presently overloaded commercial system at the AEC-TRF, a 600 kw AEC furnished diesel generator will be shipped from Damon Tract and will be installed on a concrete pier foundation south of the main substation. The main substation slab will be enlarged to accommodate three (3) new 250 kva, 120/208-4160 volt, single phase transformers. The generator will supply power to the transformers and the transformers will supply power to a new 120/208 volt, 60 cycle, 3 phase power panel. Back up capability will be provided by tieing the two existing 75 kw generators into the substation's 600 amp automatic transfer switch. The back up generators will be connected in parallel and their output will be synchronized A 30 x 30 x 14-ft. high prefabricated metal shelter will be installed over the enlarged substation. The shelter will have metal roofing but will be opensided. Chain link security fencing will enclose the new transformer portion of the substation. The FY 69 work described above is a Maintenance and Operations project. FY 1970 ENGINEERING To be accomplished. PROCUREMENT To be accomplished. CONSTRUCTION The major upgrading of the power system involving replacement of existing cables as needed, installation of new cables for planned facilities and a main breaker panel cooling system will be provided. POST -GO ENGINEERING PROCUREMENT To be accomplished. To be accomplished. CONSTRUCTION The ultimate power requirement for the AEC-TRF is estimated at 1800 kw. Complete separation of scientific loads from utility loads t1-25 VOLII