Estimate - Phase V-A.

The following estimate for Phase V-A includes

cost for replacement of the maximum amount of facilities that may be damaged
during the experiments on four shot islands.
The deduction shown following the estimate for Phase V-A has been estimated on the basis that the degree of damage to certain of the facilities
will not require this maximum replacement.

The actual cost will undoubtedly

be between these two figures.
It is assumed that activity in the center (3 inch) paved area around the
towers will be such that all of this pavement must be removed and that all

paving around towers (both 3 inch and 1-1/2 inch) will be relaid.

The deduc-

tion shown following the estimate for Phase V-A omits all paving reconstruction.

Also included in the maximm estimate is the cost of rebuilding com-

pletely all building superstructures for the outlying camps.

If it is pos-

sible to salvage this material for re-erection, the material cost can be
reduced considerably.

Replacement for the water system includes new material

and installation labor for all shot island water tanks, one-half of the pumps
and all water system buildings.
tion of pumps and stills only.

The deduction contemplates the re-installaOn the maximum estimate, it is assumed that

replacement of electrical work will include, on the shot islands, twenty
percent replacement of underground buildings, loss of all above groum power
plants and all overhead distribution lines.

The deduction estimate is on the

basis that only one-third of this loss will be sustained.

Special buildings

are included in the maximum estimate on the assumption that the second experiment might require several new buildings of types different from those originally constructed.
ings required.

The deduction assumes that there will be no such build-

All other items are considered nominal, so no credit is

reflected in the deduction.