On "P=2" Day, 6 April, all personnel except generator watches, signal equipment operators, security details and key scientists were evacuated from the three zero islands to Eniwetok, and all personnel were removed from the two Zero Islands not to be tested the following (minus one) day. Except for some minor work and cleanup, construction on Engebi and Aoman was considered complete at this time, and little Army Task Group construction remained to be done on Runit. On "P-1" Day, the evacuation groups were embarked from iniwetok as per the plan issued by CTG 7.2. The normal evacuation for Parry Island had taken place on minus two days. Standby personnel on Eniwetok and Parry, including key utility personnel, security forces, special equipment operators, drone control, light aviation and RadSafe personnel all remained ashore to carry out their missions. "Embarkation Plans" for all test days proved to be virtually the same, and only one of them is attached to this report. Units were checked aboard their respective ships by representatives of the Iscom S-3 and were accounted for again by muster after arriving aboard ship, and necessary reports made to Hq, JIF 7. One important task of TG 7.2 was to water down the coral runway on Eniwetok so that the vision of ground control crews of the Drone Planes would not be obscured by dust raised during the drone takeoffs. An average of about 10,000 gallons of sea water was used for wetting down the strip for each test operation. The practice "P" Day of 8 April was a success and later in the morning the ships re-entered the lagoon and commenced discharging their passengers about noon. SectionWI-<c. 2

Select target paragraph3