CONSTRUCTION - $815,000
Construction plans envision building 30 houses in the first year to
accommodate approximately half of the present population of Killi (360).
In the second and succeeding years through FY-75, the redevelopment plan
calls for the addition of six houses each year so that by FY-75 there
will be a total of 60 units, or sufficient housing to take care of about
360 persons.
The Bikini people want to reestablish their homes on their
original "wetos" or land holdings.
This precludes cluster or “subdivi-
sion" planning, and means that the houses will be scattered instead of
being grouped in a community complex. Estimated costs of $6,000 per
house include cistern for water catchment, cook house, toilet, bath houses,
copra crib, etc. The construction is programmed for completion in FY-70,
_ assuming funding can be arranged. The only construction scheduled for
following years is the addition of six houses each year and the addition
of expandable school facilities in FY~-1973 to take care of increased
population.
The various elements in construction cost estimates are as follows:
30 houses @ $6,000
School
Church
0
;
Meeting house
;
$ 180,000
30,000
20,000
_
Roads
15,000
-
Administrative Buildings ~
Dock repair
20,000
20,000
25,000
Airport repair
10,000
Warehouse
Equipment
/
Equipment shed .Freight and Transportation
Supervision and labor
10,000
:
*
:
Contingency
30 ,000
5,000
100,000
100 ,000
60 ,000
Total construction FY-70
i
$ 625,000
Construction schedule through FY-75:
FY-69
FY-70
FY-71
FY-72
FY-73
FY-74.
FY-75
-~-- $625,000 $ 36,000 $36,000 $46,000 $36,000 $36,000
———